5962 W 74TH ST 90045
Certificate Information: 5962 W 74TH ST 90045
- Application / Permit
- 24014-10000-04621
- Plan Check / Job No.
- B24LA27326
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: One story addition and remodel to an existing one story S.F.D. with attached garage.
- Permit Issued
- Issued on 11/14/2024
- Issuing Office
- Current Status
- CofO Issued on 3/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2024 | CAROLEAN BASMA |
| Corrections Issued | 10/19/2024 | CAROLEAN BASMA |
| Plan Check Approved | 11/14/2024 | CAROLEAN BASMA |
| Issued | 11/14/2024 | APPLICANT |
| CofO in Progress | 3/4/2025 | TEMISTOCLES CAAL |
| Permit Finaled | 3/4/2025 | RICHARD STEINBACH |
| CofO Issued | 3/4/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/4/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 10/31/2024 | DARIN LAM |
| Specific Plan | Cleared | 11/12/2024 | FREDDY GARCIA |
| Grading Pre-Inspection | Cleared | 11/14/2024 | CAROLEAN BASMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/15/2024 | Approved | TEMISTOCLES CAAL |
| Wood Frame | 11/27/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 12/2/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Deputy Wood Construction | 12/13/2024 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 12/27/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 12/27/2024 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 12/30/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 12/30/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 12/30/2024 | Approved | TEMISTOCLES CAAL |
| MERV13>=Rough | 12/30/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 12/30/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 1/3/2025 | Approved | BOBBY KEY |
| Shower Pan | 1/3/2025 | Approved | BOBBY KEY |
| Special/Order Compliance | 1/3/2025 | Partial Inspection | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 1/7/2025 | Partial Approval | TEMISTOCLES CAAL |
| Drywall Nailing | 1/13/2025 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 1/24/2025 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 2/27/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Gas Test | 2/27/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 2/27/2025 | Approved | TEMISTOCLES CAAL |
| Service/Power Release | 2/27/2025 | Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 2/27/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 2/28/2025 | Approved | TEMISTOCLES CAAL |
| Final | 2/28/2025 | OK to Issue CofO | TEMISTOCLES CAAL |
| MERV13>=Final | 2/28/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 2/28/2025 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 2/28/2025 | SGSOV Approved | TEMISTOCLES CAAL |