4312 S NEOSHO AVE 90066
Certificate Information: 4312 S NEOSHO AVE 90066
- Application / Permit
- 24014-10000-04590
- Plan Check / Job No.
- B24LA27089
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- major remodel to entire s.f.r and 483 s. ft addition. re-roof portion of existing ,, demo porch and porte-cochere , new entry porch
- Permit Issued
- Issued on 3/4/2025
- Issuing Office
- Current Status
- CofO Issued on 3/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2024 | RACHEL BEYENE |
| Corrections Issued | 10/30/2024 | RACHEL BEYENE |
| Quality Review Completed | 11/13/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 2/20/2025 | RACHEL BEYENE |
| Applicant returned to address corrections | 2/28/2025 | RACHEL BEYENE |
| Plan Check Approved | 3/3/2025 | RAHEL BEYENE |
| Issued | 3/4/2025 | APPLICANT |
| CofO in Progress | 3/6/2026 | ANTHONY EGSON |
| Permit Finaled | 3/14/2026 | RICHARD STEINBACH |
| CofO Issued | 3/14/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/14/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/2/2024 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/4/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 11/15/2024 | LIAM ODONOVAN |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | My Home Builders Inc; Lic. No.: 1002927-B | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/29/2025 | Approved | RUBEN RIVAS |
| Footing/Foundation/Slab | 4/30/2025 | Approved | RUBEN RIVAS |
| Wood Frame | 6/2/2025 | Partial Approval | RUBEN RIVAS |
| PLUMBING-Rough | 6/3/2025 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Rough | 6/5/2025 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2025 | Partial Approval | RUBEN RIVAS |
| HVAC-Rough | 7/17/2025 | Partial Approval | RUBEN RIVAS |
| BUILDING-Rough-Frame | 8/14/2025 | Corrections Issued | MICHAEL ALLEN |
| ELECTRICAL-Rough | 8/14/2025 | Corrections Issued | MICHAEL ALLEN |
| Gas Test | 8/14/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 8/14/2025 | Corrections Issued | MICHAEL ALLEN |
| PLUMBING-Rough | 8/14/2025 | Corrections Issued | MICHAEL ALLEN |
| Deputy Wood Construction | 8/19/2025 | Conditional Approval | JAYLIN GRAVITTE |
| ELECTRICAL-Rough | 8/22/2025 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 8/22/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 9/8/2025 | Approved | RUBEN RIVAS |
| Insulation | 9/18/2025 | Approved | MICHAEL ALLEN |
| Insulation | 9/22/2025 | Corrections Issued | MICHAEL ALLEN |
| Drywall Nailing | 9/30/2025 | No Access for Inspection | RUBEN RIVAS |
| Drywall Nailing | 10/3/2025 | Approved | RUBEN RIVAS |
| Shower Pan | 10/14/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 1/12/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 1/12/2026 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/12/2026 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 1/12/2026 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 1/26/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 1/26/2026 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 2/2/2026 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/13/2026 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 2/13/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 2/13/2026 | Approved | ANTHONY EGSON |
| Final | 2/26/2026 | Conditional Approval | ANTHONY EGSON |
| Final | 2/26/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 2/27/2026 | Approved | DAVID FEILER |
| Final | 3/5/2026 | OK to Issue CofO | ANTHONY EGSON |