4418 N STANSBURY AVE 91423
Certificate Information: 4418 N STANSBURY AVE 91423
- Application / Permit
- 24014-10000-04578
- Plan Check / Job No.
- B24LA27021
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN REMODEL AND ADDITION TO THE REAR OF (E) SFD
- Permit Issued
- Issued on 12/2/2024
- Issuing Office
- Current Status
- CofO Issued on 5/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2024 | JOHNPAUL ISIP |
| Corrections Issued | 10/21/2024 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 11/9/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 11/25/2024 | JOHNPAUL ISIP |
| Issued | 12/2/2024 | APPLICANT |
| Issued | 12/2/2024 | SUYA LY |
| CofO in Progress | 4/7/2025 | MISAEL ESPARZA |
| CofO Issued | 5/2/2025 | RUBEN SALAS |
| Permit Finaled | 5/2/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 11/18/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 11/18/2024 | LEE GUILBEAUX |
| ZI | Cleared | 11/21/2024 | GEORGIA SMITH |
Contact Information
| Contractor | Marco Giovanni Brambilla; Lic. No.: 544844-B | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/10/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 12/13/2024 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2024 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 1/14/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 1/14/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 1/14/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/22/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 1/22/2025 | Approved | MISAEL ESPARZA |
| Green Building Rough | 1/22/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 1/22/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 1/22/2025 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 2/3/2025 | Approved | MISAEL ESPARZA |
| Insulation | 2/3/2025 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/3/2025 | Corrections Issued | MISAEL ESPARZA |
| Shower Pan | 2/3/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/5/2025 | Approved | MISAEL ESPARZA |
| Insulation | 2/5/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/5/2025 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 2/5/2025 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 2/11/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/11/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/4/2025 | Approved | MISAEL ESPARZA |
| Final | 4/4/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/4/2025 | Approved | MISAEL ESPARZA |
| Green Building Final | 4/4/2025 | Approved | MISAEL ESPARZA |
| Green Building Rough | 4/4/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 4/4/2025 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 4/4/2025 | Approved | MISAEL ESPARZA |