3923 W EDENHURST AVE 90039
Certificate Information: 3923 W EDENHURST AVE 90039
- Application / Permit
- 24014-10000-04568
- Plan Check / Job No.
- B24LA26973
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ELAN REMODEL AND REAR ADDITION TO (E) SFD, CONVERT ATTACHED CARPORT TO GARAGE NEW COVERED PATIO AND OPENTRELLIS
- Permit Issued
- Issued on 12/17/2024
- Issuing Office
- Current Status
- CofO Issued on 9/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2024 | KHUONG TRUONG |
| Corrections Issued | 10/22/2024 | KHUONG TRUONG |
| Quality Review Completed | 10/22/2024 | GARO TELMI |
| Plan Check Approved | 12/17/2024 | KHUONG TRUONG |
| Issued | 12/17/2024 | APPLICANT |
| CofO in Progress | 9/3/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 9/4/2025 | DEROLD HAUFF |
| CofO Issued | 9/4/2025 | DEROLD HAUFF |
| Permit Finaled | 9/4/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/24/2024 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/26/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 11/26/2024 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/10/2025 | Corrections Issued | WILLIAM SIERRA |
| Pre-Inspection | 1/10/2025 | Partial Inspection | WILLIAM SIERRA |
| PLUMBING-Rough | 1/16/2025 | Corrections Issued | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 1/21/2025 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 1/21/2025 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 1/24/2025 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/18/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 2/18/2025 | Approved | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 2/18/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 2/18/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 2/24/2025 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 2/24/2025 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/24/2025 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/27/2025 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 2/27/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 2/27/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 3/5/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Shower Pan | 3/5/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Shower Pan | 3/6/2025 | Approved | JOSH MEISTER |
| Green Building Rough | 3/14/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 3/19/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 3/24/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 5/22/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 5/22/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 5/22/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| PLUMBING-Final | 5/22/2025 | Corrections Issued | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/22/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 5/22/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 8/14/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 8/14/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 8/14/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| PLUMBING-Final | 8/14/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/14/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| Service/Power Release | 8/14/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 9/2/2025 | Approved | NICHOLAS LOPEZ |
| Final | 9/2/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| Green Building Final | 9/2/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 9/2/2025 | Approved | NICHOLAS LOPEZ |