8001 S KENTWOOD AVE 90045

Certificate Information: 8001 S KENTWOOD AVE 90045

Application / Permit
24014-10000-04513
Plan Check / Job No.
B24LA26404
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO (E) 1-STORY SFD W/ ATTACHED GARAGE.
Permit Issued
Issued on 3/18/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/8/2024 APPLICANT
Assigned to Plan Check Engineer 10/10/2024 ADRIANA LOPEZ
Corrections Issued 10/17/2024 ADRIANA LOPEZ
Quality Review Completed 10/18/2024 KEN GILL
Building Plans Picked Up 11/14/2024 APPLICANT
Applicant returned to address corrections 1/29/2025 ADRIANA LOPEZ
Plan Check Approved 3/6/2025 ADRIANA LOPEZ
Issued 3/18/2025 APPLICANT
CofO in Progress 2/25/2026 ANTHONY EGSON
Permit Finaled 3/3/2026 RICHARD STEINBACH
CofO Issued 3/3/2026 RICHARD STEINBACH
Permit Finaled 3/3/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/11/2025 XOCHITL ARQUIETA
Roof/Waste drainage to street Cleared 2/11/2025 XOCHITL ARQUIETA
Specific Plan Cleared 2/14/2025 JOSHUA JONES

Contact Information

Architect Borden,, Gail Peter; Lic. No.: C32191 1918 LAUDERDALE STREET      HOUSTON, TX 77030
Contractor Byrne John P Construction; Lic. No.: 630810-B 8449 KITTYHAWK AVENUE      LOS ANGELES, CA 90045
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/7/2025 Partial Approval RUBEN RIVAS
METHANE-Barrier 4/7/2025 Not Ready for Inspection RUBEN RIVAS
METHANE-Subgrade 4/7/2025 Not Ready for Inspection RUBEN RIVAS
PLUMBING-Rough 4/14/2025 Partial Approval RUBEN RIVAS
BUILDING-Rough-Frame 5/27/2025 Not Ready for Inspection RUBEN RIVAS
Green Building Rough 5/27/2025 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Rough 5/28/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/28/2025 Corrections Issued JESUS PINEDA
HVAC-Rough 5/28/2025 Approved JESUS PINEDA
PLUMBING-Rough 5/28/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 6/3/2025 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 6/3/2025 Approved RUBEN RIVAS
Green Building Rough 6/3/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 6/3/2025 Partial Approval RUBEN RIVAS
Insulation 6/6/2025 Approved RUBEN RIVAS
Drywall Nailing 6/17/2025 Approved RUBEN RIVAS
ELECTRICAL-Final 8/28/2025 Approved RUBEN RIVAS
Final 8/28/2025 Corrections Issued RUBEN RIVAS
Footing/Foundation/Slab 8/28/2025 Approved RUBEN RIVAS
Green Building Final 8/28/2025 Approved RUBEN RIVAS
PLUMBING-Final 8/28/2025 Approved RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 8/28/2025 SGSOV Approved RUBEN RIVAS
Smoke Detectors 8/28/2025 Approved RUBEN RIVAS
Final 2/24/2026 OK to Issue CofO ANTHONY EGSON