7720 S WESTLAWN AVE 90045

Certificate Information: 7720 S WESTLAWN AVE 90045

Application / Permit
24014-10000-04490
Plan Check / Job No.
B24LA26269
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
- New 2 story ADU addition to existing rear yard detached Garage PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 12/24/2024
Issuing Office
Current Status
CofO Issued on 1/6/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2024 APPLICANT
Assigned to Plan Check Engineer 10/17/2024 VARAND SARKISIAN
Corrections Issued 10/22/2024 VARAND SARKISIAN
Quality Review Completed 10/25/2024 GARO TELMI
Plan Check Approved 12/24/2024 VARAND SARKISIAN
Issued 12/24/2024 APPLICANT
CofO in Progress 1/6/2026 JESUS PINEDA
Permit Finaled 1/6/2026 RICHARD STEINBACH
CofO Issued 1/6/2026 RICHARD STEINBACH
Permit Finaled 1/6/2026 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 11/5/2024 RICHARD WOO
Address approval Cleared 11/8/2024 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 11/8/2024 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 11/8/2024 MANUEL TEJADA
Roof/Waste drainage to street Cleared 11/8/2024 ANTHONY MAINEZ
Sewer availability Cleared 11/8/2024 ANTHONY MAINEZ
Construction near power lines Cleared 11/25/2024 RIDWAN HARDY

Contact Information

Contractor Chadwick & Doggett General Contracting Inc; Lic. No.: 756093-B       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/17/2025 Partial Approval TEMISTOCLES CAAL
Deputy Drilled-In Anchors 1/27/2025 Partial Approval MICHAEL ALLEN
Footing/Foundation/Slab 1/29/2025 Partial Approval MICHAEL ALLEN
PLUMBING-Rough 2/6/2025 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Corrections Issued TEMISTOCLES CAAL
Special/Order Compliance 2/25/2025 Corrections Issued TEMISTOCLES CAAL
Deputy Wood Construction 2/26/2025 Conditional Approval TEMISTOCLES CAAL
Deputy Wood Construction 3/19/2025 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/15/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/1/2025 Partial Approval TEMISTOCLES CAAL
Underground Mechanical 5/1/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 5/6/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/6/2025 Approved JESUS PINEDA
HVAC-Rough 5/6/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 5/13/2025 Partial Approval RUBEN RIVAS
PLUMBING-Rough 5/13/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 5/20/2025 Partial Approval JAYLIN GRAVITTE
BUILDING-Rough-Frame 5/27/2025 Approved JESUS RODRIGUEZ
Insulation 5/27/2025 Approved JESUS RODRIGUEZ
Special/Order Compliance 5/27/2025 Corrections Issued JESUS RODRIGUEZ
Drywall Nailing 6/4/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 6/11/2025 Approved JESUS PINEDA
Shower Pan 6/11/2025 Approved JESUS PINEDA
Gas Test 9/10/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 9/10/2025 SGSOV Approved JESUS PINEDA
ELECTRICAL-Final 10/9/2025 Approved JESUS PINEDA
HVAC-Final 10/9/2025 Approved JESUS PINEDA
PLUMBING-Final 10/9/2025 Approved JESUS PINEDA
Service/Power Release 10/9/2025 Approved JESUS PINEDA
Final 1/5/2026 OK to Issue CofO JESUS PINEDA
Footing/Foundation/Slab 1/5/2026 Approved JESUS PINEDA
Smoke Detectors 1/5/2026 Approved JESUS PINEDA
Special/Order Compliance 1/5/2026 Partial Inspection DAKOTA LOW