5529 W 79TH ST 90045

Certificate Information: 5529 W 79TH ST 90045

Application / Permit
24014-10000-04477
Plan Check / Job No.
B24LA26178
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
[ePlan] major remodel and addition to (E) 1-Story SFD with new attached 1-car garage. -Bldg Sprinklered Thru-out
Permit Issued
Issued on 12/14/2024
Issuing Office
Current Status
CofO Issued on 9/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2024 APPLICANT
Assigned to Plan Check Engineer 10/10/2024 MAHNAZ NOURHASHEMI
Corrections Issued 10/14/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 10/21/2024 TU HUA
Applicant returned to address corrections 11/6/2024 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 11/20/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 12/13/2024 MAHNAZ NOURHASHEMI
Issued 12/14/2024 APPLICANT
CofO in Progress 9/22/2025 JESUS PINEDA
Permit Finaled 9/25/2025 RICHARD STEINBACH
CofO Issued 9/25/2025 RICHARD STEINBACH
Permit Finaled 9/25/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/21/2024 ANTHONY MAINEZ
Sewer availability Cleared 10/21/2024 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 10/22/2024 LIAM ODONOVAN
Grading Pre-Inspection Cleared 10/22/2024 VASIL MIHALEV
Specific Plan Cleared 10/25/2024 RICHARD WOO
GPI Written Notices Cleared 12/13/2024 MAHNAZ NOURHASHEMI

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Architect Noteware,, Brian Arthur; Lic. No.: NA21514       ,
Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/10/2025 Corrections Issued TEMISTOCLES CAAL
Sewer 1/10/2025 Corrections Issued TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 1/17/2025 Corrections Issued TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 1/22/2025 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 1/24/2025 Approved BOBBY KEY
METHANE-Barrier 1/24/2025 Approved BOBBY KEY
Special/Order Compliance 2/19/2025 Partial Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 2/27/2025 Corrections Issued TEMISTOCLES CAAL
BUILDING-Rough-Frame 3/10/2025 Corrections Issued JESUS PINEDA
Deputy Wood Construction 3/10/2025 Approved JESUS PINEDA
ELECTRICAL-Rough 3/10/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 Not Ready for Inspection JESUS PINEDA
Green Building Rough 3/10/2025 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 3/10/2025 Corrections Issued JESUS PINEDA
PLUMBING-Rough 3/10/2025 Corrections Issued JESUS PINEDA
Verify Sprinkler Sign Off 3/10/2025 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 3/20/2025 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Rough 3/20/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/20/2025 Approved JESUS PINEDA
Green Building Rough 3/20/2025 Approved JESUS PINEDA
HVAC-Rough 3/20/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 3/20/2025 Partial Approval JESUS PINEDA
PLUMBING-Rough 3/20/2025 Not Ready for Inspection JESUS PINEDA
Verify Sprinkler Sign Off 3/20/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 3/27/2025 Approved JESUS PINEDA
Insulation 3/27/2025 Approved JESUS PINEDA
PLUMBING-Rough 3/27/2025 Approved JESUS PINEDA
Drywall Nailing 4/2/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 4/2/2025 Approved JESUS PINEDA
Shower Pan 4/2/2025 Approved JESUS PINEDA
ELECTRICAL-Final 9/12/2025 Corrections Issued JESUS PINEDA
Final 9/12/2025 Corrections Issued JESUS PINEDA
Green Building Final 9/12/2025 Approved JESUS PINEDA
HVAC-Final 9/12/2025 Corrections Issued JESUS PINEDA
PLUMBING-Final 9/12/2025 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Approved JESUS PINEDA
Smoke Detectors 9/12/2025 Approved JESUS PINEDA
ELECTRICAL-Final 9/16/2025 Approved JESUS PINEDA
Final 9/16/2025 Not Ready for Inspection JESUS PINEDA
Gas Test 9/16/2025 Corrections Issued JESUS PINEDA
HVAC-Final 9/16/2025 Approved JESUS PINEDA
PLUMBING-Final 9/16/2025 Approved JESUS PINEDA
Final 9/22/2025 OK to Issue CofO JESUS PINEDA
Service/Power Release 9/22/2025 Approved JESUS PINEDA