5529 W 79TH ST 90045
Certificate Information: 5529 W 79TH ST 90045
- Application / Permit
- 24014-10000-04477
- Plan Check / Job No.
- B24LA26178
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- [ePlan] major remodel and addition to (E) 1-Story SFD with new attached 1-car garage. -Bldg Sprinklered Thru-out
- Permit Issued
- Issued on 12/14/2024
- Issuing Office
- Current Status
- CofO Issued on 9/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/14/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 10/21/2024 | TU HUA |
| Applicant returned to address corrections | 11/6/2024 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 11/20/2024 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 12/13/2024 | MAHNAZ NOURHASHEMI |
| Issued | 12/14/2024 | APPLICANT |
| CofO in Progress | 9/22/2025 | JESUS PINEDA |
| Permit Finaled | 9/25/2025 | RICHARD STEINBACH |
| CofO Issued | 9/25/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/25/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2024 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 10/21/2024 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 10/22/2024 | LIAM ODONOVAN |
| Grading Pre-Inspection | Cleared | 10/22/2024 | VASIL MIHALEV |
| Specific Plan | Cleared | 10/25/2024 | RICHARD WOO |
| GPI Written Notices | Cleared | 12/13/2024 | MAHNAZ NOURHASHEMI |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Architect | Noteware,, Brian Arthur; Lic. No.: NA21514 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/10/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Sewer | 1/10/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 1/17/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 1/22/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 1/24/2025 | Approved | BOBBY KEY |
| METHANE-Barrier | 1/24/2025 | Approved | BOBBY KEY |
| Special/Order Compliance | 2/19/2025 | Partial Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2025 | Corrections Issued | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 3/10/2025 | Corrections Issued | JESUS PINEDA |
| Deputy Wood Construction | 3/10/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 3/10/2025 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Rough | 3/10/2025 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Rough | 3/10/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 3/10/2025 | Corrections Issued | JESUS PINEDA |
| Verify Sprinkler Sign Off | 3/10/2025 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 3/20/2025 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Rough | 3/20/2025 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2025 | Approved | JESUS PINEDA |
| Green Building Rough | 3/20/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 3/20/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 3/20/2025 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 3/20/2025 | Not Ready for Inspection | JESUS PINEDA |
| Verify Sprinkler Sign Off | 3/20/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 3/27/2025 | Approved | JESUS PINEDA |
| Insulation | 3/27/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 3/27/2025 | Approved | JESUS PINEDA |
| Drywall Nailing | 4/2/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 4/2/2025 | Approved | JESUS PINEDA |
| Shower Pan | 4/2/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 9/12/2025 | Corrections Issued | JESUS PINEDA |
| Final | 9/12/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 9/12/2025 | Approved | JESUS PINEDA |
| HVAC-Final | 9/12/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 9/12/2025 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 9/12/2025 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 9/12/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 9/16/2025 | Approved | JESUS PINEDA |
| Final | 9/16/2025 | Not Ready for Inspection | JESUS PINEDA |
| Gas Test | 9/16/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 9/16/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 9/16/2025 | Approved | JESUS PINEDA |
| Final | 9/22/2025 | OK to Issue CofO | JESUS PINEDA |
| Service/Power Release | 9/22/2025 | Approved | JESUS PINEDA |