5864 N JAMIESON AVE 91316
Certificate Information: 5864 N JAMIESON AVE 91316
- Application / Permit
- 24014-10000-04464
- Plan Check / Job No.
- B24LA26067
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN. MAJOR REMODEL AND ADDITION TO (E) 1-STORY SFD W/ ATTACHED GARAGE.
- Permit Issued
- Issued on 1/3/2025
- Issuing Office
- Current Status
- CofO Issued on 7/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2024 | ADRIANA LOPEZ |
| Corrections Issued | 10/25/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 11/15/2024 | CAROLYNN NEPOMUCENO |
| Applicant returned to address corrections | 12/23/2024 | ADRIANA LOPEZ |
| Plan Check Approved | 1/3/2025 | ADRIANA LOPEZ |
| Issued | 1/3/2025 | APPLICANT |
| CofO in Progress | 7/8/2025 | MORRIS JACKSON |
| Permit Finaled | 7/21/2025 | DANIEL ORRANTE |
| CofO Issued | 7/21/2025 | DANIEL ORRANTE |
| Permit Finaled | 7/21/2025 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/13/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/13/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Elm Construction; Lic. No.: 1099704-B | , |
| Contractor | Elm Group La Inc; Lic. No.: 1099704-B | , |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/14/2025 | Corrections Issued | MORRIS JACKSON |
| Footing/Foundation/Slab | 1/14/2025 | Approved | MORRIS JACKSON |
| Pre-Inspection | 1/14/2025 | Partial Inspection | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 1/15/2025 | Conditional Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 2/4/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 2/4/2025 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 2/4/2025 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 2/4/2025 | Partial Approval | MORRIS JACKSON |
| Sewer | 2/4/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Underground Mechanical | 2/4/2025 | Partial Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 2/13/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2025 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 2/13/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Wood Frame | 2/13/2025 | Not Ready for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 3/10/2025 | Not Ready for Inspection | MORRIS JACKSON |
| ELECTRICAL-Rough | 3/10/2025 | Corrections Issued | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 3/10/2025 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 3/10/2025 | Not Ready for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 3/28/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Deputy Wood Construction | 3/28/2025 | Conditional Approval | MORRIS JACKSON |
| ELECTRICAL-Rough | 3/28/2025 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2025 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 3/28/2025 | Not Ready for Inspection | MORRIS JACKSON |
| HVAC-Rough | 3/28/2025 | Partial Approval | MORRIS JACKSON |
| PLUMBING-Rough | 3/28/2025 | Approved | MORRIS JACKSON |
| Wood Frame | 3/28/2025 | Not Ready for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 4/3/2025 | Corrections Issued | MORRIS JACKSON |
| Interior/Exterior Lathing | 4/3/2025 | Partial Approval | MORRIS JACKSON |
| Shower Pan | 4/3/2025 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 4/7/2025 | Approved | MORRIS JACKSON |
| Green Building Rough | 4/7/2025 | Approved | MORRIS JACKSON |
| Insulation | 4/7/2025 | Approved | MORRIS JACKSON |
| Drywall Nailing | 4/16/2025 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 5/1/2025 | Approved | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 5/28/2025 | Conditional Approval | MORRIS JACKSON |
| Final | 7/1/2025 | Corrections Issued | MORRIS JACKSON |
| Green Building Final | 7/1/2025 | Approved | MORRIS JACKSON |
| HVAC-Final | 7/1/2025 | Approved | MORRIS JACKSON |
| PLUMBING-Final | 7/1/2025 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 7/1/2025 | SGSOV Approved | MORRIS JACKSON |
| Service/Power Release | 7/1/2025 | Approved | MORRIS JACKSON |
| Smoke Detectors | 7/1/2025 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 7/8/2025 | Approved | MORRIS JACKSON |
| Final | 7/8/2025 | OK to Issue CofO | MORRIS JACKSON |
| HVAC-Final | 7/8/2025 | Approved | MORRIS JACKSON |
| PLUMBING-Final | 7/8/2025 | Approved | MORRIS JACKSON |