2047 N ALMADALE AVE 90032

Certificate Information: 2047 N ALMADALE AVE 90032

Application / Permit
24014-10000-04460
Plan Check / Job No.
B24LA26045
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: NEW REAR ADDITION TO THE (E) SINGLE FAMILY DWELLING. TO REMOVE THE (E) 20'x19' ATTACHED PATIO COVER. ALL WORK PER ENG NFPA 13-D FIRE SPRINKLERS REQUIRED THRU-OUT.
Permit Issued
Issued on 4/23/2025
Issuing Office
Current Status
CofO Issued on 5/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2024 APPLICANT
Assigned to Plan Check Engineer 10/9/2024 ZAW HAN
Corrections Issued 10/10/2024 ZAW HAN
Applicant returned to address corrections 11/26/2024 GIOVANNY CHAVEZ
Plan Check Approved 12/19/2024 LUISANGEL VALENZUELA
Issued 4/23/2025 APPLICANT
CofO in Progress 5/11/2026 LILIANA PORTILLO
Permit Finaled 5/12/2026 DEROLD HAUFF
CofO Issued 5/12/2026 DEROLD HAUFF
Permit Finaled 5/12/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/24/2024 CELINA MORENO
Sewer availability Cleared 10/24/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 10/25/2024 CELINA MORENO
Construction near power lines Cleared 11/23/2024 ENRIQUE ACOSTA
GPI Written Notices Cleared 11/26/2024 ZAW HAN
Grading Pre-Inspection Cleared 11/26/2024 ZAW HAN

Contact Information

Contractor Owner-Builder       ,
Engineer Jalalpour,, Mohammad; Lic. No.: S6696 2610 VISTA DEL ORO      NEWPORT BEACH, CA 92660

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/21/2025 Partial Inspection LILIANA PORTILLO
Deputy Drilled-In Anchors 8/15/2025 Conditional Approval LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 9/4/2025 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 9/4/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 9/4/2025 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 10/2/2025 Partial Approval LILIANA PORTILLO
Insulation 10/2/2025 Partial Approval LILIANA PORTILLO
Wood Frame 10/8/2025 Partial Approval RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 10/27/2025 Corrections Issued BRENDAN MORELLI
HVAC-Rough 11/13/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 11/13/2025 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 12/2/2025 Approved LILIANA PORTILLO
ELECTRICAL-Rough 12/2/2025 Approved LILIANA PORTILLO
HVAC-Rough 12/2/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 12/2/2025 Approved LILIANA PORTILLO
Insulation 12/5/2025 Approved GEM DE OCAMPO
Interior/Exterior Lathing 12/5/2025 Partial Approval GEM DE OCAMPO
Drywall Nailing 12/8/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 12/8/2025 Partial Approval LILIANA PORTILLO
Interior/Exterior Lathing 12/11/2025 Not Ready for Inspection GEM DE OCAMPO
Shower Pan 12/11/2025 Approved GEM DE OCAMPO
BUILDING-Rough-Frame 4/1/2026 Approved LILIANA PORTILLO
Final 4/1/2026 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 4/1/2026 Approved LILIANA PORTILLO
Green Building Final 4/1/2026 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 4/1/2026 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/1/2026 SGSOV Approved LILIANA PORTILLO
Smoke Detectors 4/1/2026 Approved LILIANA PORTILLO
ELECTRICAL-Final 5/7/2026 Approved LILIANA PORTILLO
Final 5/7/2026 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 5/7/2026 Approved LILIANA PORTILLO
HVAC-Final 5/7/2026 Approved LILIANA PORTILLO
PLUMBING-Final 5/7/2026 Approved LILIANA PORTILLO
Service/Power Release 5/7/2026 Approved LILIANA PORTILLO
Final 5/8/2026 OK to Issue CofO LILIANA PORTILLO
Green Building Final 5/8/2026 Approved LILIANA PORTILLO