5341 N CANDACE PL 90041

Certificate Information: 5341 N CANDACE PL 90041

Application / Permit
24014-10000-04444
Plan Check / Job No.
B24LA25920
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN REMODEL (E) SFD & REAR PATIO ADDITION.
Permit Issued
Issued on 2/12/2025
Issuing Office
Current Status
Issued on 2/12/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/4/2024 APPLICANT
Assigned to Plan Check Engineer 10/17/2024 ADRIANA LOPEZ
Corrections Issued 10/28/2024 ADRIANA LOPEZ
Quality Review Completed 11/15/2024 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 1/30/2025 ADRIANA LOPEZ
Plan Check Approved 2/6/2025 ADRIANA LOPEZ
Issued 2/12/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/11/2024 LANNY MERRICK
Roof/Waste drainage to street Cleared 12/19/2024 DAVID LOPEZ
Sewer availability Cleared 12/19/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 12/26/2024 DAVID LOPEZ

Contact Information

Architect Salas,, Rafael; Lic. No.: C35683       WHITTIER, CA 90605
Contractor Hill Rich; Lic. No.: 1064783-B       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/19/2025 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 2/19/2025 Partial Approval BRENDAN MORELLI
BUILDING-Rough-Frame 3/28/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Rough 3/28/2025 Not Ready for Inspection NICHOLAS LOPEZ
Rough-Elec/Plmb/HVAC 3/28/2025 Corrections Issued NICHOLAS LOPEZ
Shower Pan 3/28/2025 Partial Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 5/29/2025 Not Ready for Inspection DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 5/29/2025 Partial Approval DAVID WILLIAMS
Footing/Foundation/Slab 5/29/2025 Partial Approval DAVID WILLIAMS
Green Building Rough 5/29/2025 Not Ready for Inspection DAVID WILLIAMS
Rough-Elec/Plmb/HVAC 5/29/2025 Not Ready for Inspection DAVID WILLIAMS
Shower Pan 5/29/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 6/13/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Drywall Nailing 6/13/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 6/13/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Insulation 6/13/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 6/13/2025 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 6/24/2025 Not Ready for Inspection DAVID WILLIAMS
Drywall Nailing 6/24/2025 Partial Approval DAVID WILLIAMS
Green Building Rough 6/24/2025 Not Ready for Inspection DAVID WILLIAMS
Insulation 6/24/2025 Partial Approval DAVID WILLIAMS
Rough-Elec/Plmb/HVAC 6/24/2025 Partial Inspection DAVID WILLIAMS
Drywall Nailing 7/10/2025 Partial Approval GEM DE OCAMPO
Green Building Rough 7/10/2025 Partial Approval GEM DE OCAMPO
Insulation 7/10/2025 Partial Approval GEM DE OCAMPO
Interior/Exterior Lathing 7/10/2025 Not Ready for Inspection GEM DE OCAMPO
Drywall Nailing 7/17/2025 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 7/17/2025 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/8/2025 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 8/20/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 9/5/2025 Partial Approval JEFFREY MEAD
Interior/Exterior Lathing 9/26/2025 Approved GEM DE OCAMPO
BUILDING-Rough-Frame 10/8/2025 Not Ready for Inspection DAVID WILLIAMS
Green Building Rough 10/8/2025 Approved DAVID WILLIAMS
Insulation 10/20/2025 Approved RONNIE MEDINA
Drywall Nailing 10/24/2025 Partial Approval GEM DE OCAMPO
Interior/Exterior Lathing 10/24/2025 Approved GEM DE OCAMPO
Underground Mechanical 11/18/2025 Approved RONNIE MEDINA
ELECTRICAL-Rough 11/20/2025 Not Ready for Inspection RONNIE MEDINA
HVAC-Rough 11/20/2025 Not Ready for Inspection RONNIE MEDINA
PLUMBING-Rough 11/20/2025 Not Ready for Inspection RONNIE MEDINA
ELECTRICAL-Rough 11/21/2025 Not Ready for Inspection RONNIE MEDINA
PLUMBING-Rough 11/21/2025 Not Ready for Inspection RONNIE MEDINA
Wood Frame 11/21/2025 Corrections Issued RONNIE MEDINA
BUILDING-Rough-Frame 11/24/2025 Approved RONNIE MEDINA
ELECTRICAL-Rough 11/24/2025 Approved RONNIE MEDINA
HVAC-Rough 11/24/2025 Approved RONNIE MEDINA
PLUMBING-Rough 11/24/2025 Approved RONNIE MEDINA
Insulation 12/1/2025 Approved RONNIE MEDINA
Shower Pan 12/1/2025 Approved RONNIE MEDINA
Drywall Nailing 5/6/2026 Approved RONNIE MEDINA
Final 5/6/2026 Corrections Issued RONNIE MEDINA
Green Building Final 5/6/2026 Approved RONNIE MEDINA
SGSOV-Seismic Gas S/O Valve 5/6/2026 SGSOV Not Ready RONNIE MEDINA
Smoke Detectors 5/6/2026 Approved RONNIE MEDINA