4808 N RUTH AVE 90041
Certificate Information: 4808 N RUTH AVE 90041
- Application / Permit
- 24014-10000-04442
- Plan Check / Job No.
- B24LA25869
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED 1-CAR GARAGE INTO ACCESSORY DWELLING UNIT AND 2-STORY ADDITION PER LAMC 12.22A.33(c)-(d)
- Permit Issued
- Issued on 4/2/2025
- Issuing Office
- Current Status
- CofO Issued on 11/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2024 | VIVIAN LAO |
| Corrections Issued | 10/22/2024 | VIVIAN LAO |
| Quality Review Completed | 10/24/2024 | KEN GILL |
| Building Plans Picked Up | 10/25/2024 | APPLICANT |
| Applicant returned to address corrections | 2/21/2025 | VIVIAN LAO |
| Plan Check Approved | 3/13/2025 | VIVIAN LAO |
| Issued | 4/2/2025 | APPLICANT |
| CofO in Progress | 11/13/2025 | DAVID WILLIAMS |
| Permit Finaled | 11/14/2025 | DEROLD HAUFF |
| CofO Issued | 11/14/2025 | DEROLD HAUFF |
| Permit Finaled | 11/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/16/2024 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 11/16/2024 | TREVOR QUAN |
| Miscellaneous | Cleared | 11/18/2024 | ANNA VIDAL |
| Miscellaneous | Cleared | 1/23/2025 | ALBERT TAM |
| Miscellaneous | Cleared | 1/23/2025 | ALBERT TAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2025 | TREVOR QUAN |
| Sewer availability | Cleared | 2/3/2025 | TREVOR QUAN |
| GPI Written Notices | Cleared | 3/13/2025 | VIVIAN LAO |
| Grading Pre-Inspection | Cleared | 3/13/2025 | MICHAEL TEMPLE |
Contact Information
| Contractor | Nextgen Home Builders Inc; Lic. No.: 1104838-B | 1540 N BRONSON AVE #6 LOS ANGELES, CA 90028 |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 5/6/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Underground Mechanical | 5/6/2025 | Approved | DAVID WILLIAMS |
| Deputy Drilled-In Anchors | 5/9/2025 | Conditional Approval | JEFFREY MEAD |
| Deputy Reinf. Concrete | 5/9/2025 | Conditional Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 5/9/2025 | Corrections Issued | JEFFREY MEAD |
| Footing/Foundation/Slab | 6/2/2025 | Corrections Issued | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Approved | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2025 | Partial Approval | DAVID WILLIAMS |
| ELECTRICAL-Rough | 7/3/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 7/3/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Rough | 7/3/2025 | Approved | NICHOLAS LOPEZ |
| Sewer | 7/14/2025 | Partial Approval | LILIANA PORTILLO |
| Underground Mechanical | 7/14/2025 | Partial Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/18/2025 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2025 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 7/18/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/24/2025 | Conditional Approval | JEFFREY MEAD |
| Green Building Rough | 7/24/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 7/24/2025 | Approved | JEFFREY MEAD |
| Insulation | 7/24/2025 | Corrections Issued | JEFFREY MEAD |
| Interior/Exterior Lathing | 7/24/2025 | Approved | JEFFREY MEAD |
| Shower Pan | 7/24/2025 | Approved | JEFFREY MEAD |
| Drywall Nailing | 8/5/2025 | Conditional Approval | GEM DE OCAMPO |
| BUILDING-Rough-Frame | 11/3/2025 | Approved | RONNIE MEDINA |
| Drywall Nailing | 11/3/2025 | Approved | RONNIE MEDINA |
| Final | 11/3/2025 | Corrections Issued | RONNIE MEDINA |
| Footing/Foundation/Slab | 11/3/2025 | Partial Inspection | RONNIE MEDINA |
| Green Building Final | 11/3/2025 | Not Ready for Inspection | RONNIE MEDINA |
| SGSOV-Seismic Gas S/O Valve | 11/3/2025 | SGSOV Approved | RONNIE MEDINA |
| Smoke Detectors | 11/3/2025 | Approved | RONNIE MEDINA |
| Final | 11/7/2025 | Corrections Issued | DAVID WILLIAMS |
| Footing/Foundation/Slab | 11/7/2025 | Approved | DAVID WILLIAMS |
| Green Building Final | 11/7/2025 | Approved | DAVID WILLIAMS |
| Final | 11/13/2025 | OK to Issue CofO | DAVID WILLIAMS |