17153 W ADLON ROAD 91436

Certificate Information: 17153 W ADLON ROAD 91436

Application / Permit
24014-10000-04429
Plan Check / Job No.
B24LA25709
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) 2ND FLOOR, MASTER BATH REMODEL, KITCHEN REMODEL, ADD CLOSET TO BEDROOM #1, NEW LAUNDRY
Permit Issued
Issued on 12/3/2024
Issuing Office
Metro
Current Status
Issued on 12/3/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/3/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 JOE VO
Corrections Issued 10/9/2024 JOE VO
Quality Review Completed 10/18/2024 KEN GILL
Building Plans Picked Up 10/28/2024 APPLICANT
Plan Check Approved 11/19/2024 JOE VO
Issued 12/3/2024 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 11/7/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 11/7/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 11/7/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 11/7/2024 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 11/7/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 11/7/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 11/8/2024 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 11/8/2024 SERGIO VALENZUELA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/9/2025 Corrections Issued THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 1/28/2025 Partial Approval JOHN COLEMAN
Deputy Drilled-In Anchors 2/3/2025 Conditional Approval HENRY KIM
Deputy Other (see comments) 2/3/2025 Conditional Approval HENRY KIM
Footing/Foundation/Slab 2/4/2025 Corrections Issued HENRY KIM
Deputy Steel/Welding 2/5/2025 No Access for Inspection THOMAS FINNILA
Deputy Reinf. Concrete 2/6/2025 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 2/20/2025 Corrections Issued JON MCHUGH
PLUMBING-Rough 2/24/2025 Conditional Approval THOMAS FINNILA
HVAC-Rough 2/27/2025 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 2/28/2025 Partial Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Partial Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 3/5/2025 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/12/2025 Partial Approval SEAN WIRCH
HVAC-Rough 3/12/2025 Approved SEAN WIRCH
BUILDING-Rough-Frame 3/21/2025 Corrections Issued THOMAS FINNILA
Green Building Rough 3/21/2025 Approved THOMAS FINNILA
Insulation 3/26/2025 Approved THOMAS FINNILA
Interior/Exterior Lathing 3/26/2025 Partial Approval THOMAS FINNILA
Shower Pan 3/26/2025 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 4/3/2025 Approved THOMAS FINNILA
Drywall Nailing 4/3/2025 Approved THOMAS FINNILA
Shower Pan 4/3/2025 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 4/9/2025 Approved HENRY KIM
Shower Pan 4/9/2025 Approved HENRY KIM