15561 W AQUA VERDE DR 90077
Certificate Information: 15561 W AQUA VERDE DR 90077
- Application / Permit
- 24014-10000-04423
- Plan Check / Job No.
- B24LA25621
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* GROUND FLOOR ADDITION (ZC: 183 SF) AND REMODEL OF (E) 2-STORY SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 1/21/2025
- Issuing Office
- Current Status
- CofO Issued on 9/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | VIVIAN LAO |
| Corrections Issued | 10/8/2024 | VIVIAN LAO |
| Quality Review Completed | 10/9/2024 | GARO TELMI |
| Applicant returned to address corrections | 11/1/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 12/18/2024 | VIVIAN LAO |
| Applicant returned to address corrections | 1/15/2025 | VIVIAN LAO |
| Plan Check Approved | 1/21/2025 | VIVIAN LAO |
| Issued | 1/21/2025 | APPLICANT |
| CofO in Progress | 9/22/2025 | CARLOS MATAMOROS |
| Permit Finaled | 9/25/2025 | RICHARD STEINBACH |
| CofO Issued | 9/25/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/25/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/9/2024 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 10/9/2024 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 10/10/2024 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 12/30/2024 | JOHN CONNEALLY |
| Specific Plan | Cleared | 1/8/2025 | TIFFANY CORRALES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khansa,, Eyass; Lic. No.: C91758 | 2252 JOSIE AVE LONG BEACH, CA 90815 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/27/2025 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/27/2025 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 1/27/2025 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 2/20/2025 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 2/20/2025 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 3/27/2025 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 4/15/2025 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 4/15/2025 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 4/15/2025 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/18/2025 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/18/2025 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 4/18/2025 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/21/2025 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 4/21/2025 | Approved | CARLOS MATAMOROS |
| Insulation | 4/21/2025 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 4/22/2025 | Conditional Approval | STEPHANIE SWANSON |
| Green Building Rough | 4/22/2025 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 5/1/2025 | Approved | CARLOS MATAMOROS |
| Gas Test | 5/1/2025 | Approved | CARLOS MATAMOROS |
| Shower Pan | 5/9/2025 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 5/16/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 7/24/2025 | Not Ready for Inspection | SEAN HAUPT |
| Special/Order Compliance | 7/24/2025 | Partial Inspection | SEAN HAUPT |
| Gas Test | 8/11/2025 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Final | 9/12/2025 | Approved | CARLOS MATAMOROS |
| Final | 9/12/2025 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 9/12/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 9/12/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 9/12/2025 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/12/2025 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 9/12/2025 | Approved | CARLOS MATAMOROS |
| Final | 9/22/2025 | OK to Issue CofO | CARLOS MATAMOROS |
| HVAC-Final | 9/22/2025 | Approved | CARLOS MATAMOROS |