9661 N SANDUSKY AVE 91331
Certificate Information: 9661 N SANDUSKY AVE 91331
- Application / Permit
- 24014-10000-04412
- Plan Check / Job No.
- B24LA25511
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO ADU AND ADDITION PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 4/28/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | SAMUEL GONZALEZ |
| Corrections Issued | 10/5/2024 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 10/10/2024 | APPLICANT |
| Applicant returned to address corrections | 10/22/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 1/17/2025 | JOSEPH RAFOLS |
| Issued | 4/28/2025 | APPLICANT |
| CofO in Progress | 1/30/2026 | MICHEL ABAJAN |
| Permit Finaled | 2/17/2026 | RUBEN SALAS |
| CofO Issued | 2/17/2026 | RUBEN SALAS |
| Permit Finaled | 2/17/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 10/19/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/23/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 1/14/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 1/14/2025 | GEVORK KARAPETYAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2025 | CARLOS AGUILERA |
Contact Information
| Architect | Brier,, Jonathan Francis; Lic. No.: C34001 | 6238 BERTHA STREET LOS ANGELES, CA 90042 |
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 450 NORTH BRAND BLVD STE 600 GLENDALE, CA 91203 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/2/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/15/2025 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 5/15/2025 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/20/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/17/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/17/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 6/17/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 6/17/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/17/2025 | Approved | MICHEL ABAJAN |
| Shower Pan | 6/17/2025 | Approved | MICHEL ABAJAN |
| Insulation | 6/24/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/24/2025 | Approved | MICHEL ABAJAN |
| Shower Pan | 6/24/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/26/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 8/4/2025 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 8/15/2025 | Partial Approval | MICHEL ABAJAN |
| Final | 8/26/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 8/26/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 8/26/2025 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 8/26/2025 | Approved | MICHEL ABAJAN |
| Final | 9/4/2025 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Final | 1/29/2026 | Approved | MICHEL ABAJAN |
| Final | 1/29/2026 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 1/29/2026 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 1/29/2026 | Approved | MICHEL ABAJAN |