700 N RADCLIFFE AVE 90272

Certificate Information: 700 N RADCLIFFE AVE 90272

Application / Permit
24014-10000-04399
Plan Check / Job No.
B24LA25325
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
**2025 WILDFIRE PROJECT** MAJOR REMODEL AND ADDITION TO (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 6/24/2025
Issuing Office
West Los Angeles
Current Status
Issued on 6/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/1/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 DANIEL YIP
Corrections Issued 10/7/2024 DANIEL YIP
Quality Review Completed 10/9/2024 KEN GILL
Building Plans Picked Up 10/11/2024 APPLICANT
Applicant returned to address corrections 5/28/2025 DANIEL YIP
Plan Check Approved 6/18/2025 DANIEL YIP
Issued 6/24/2025 APPLICANT

Permit Application Clearance Information

Low Impact Development (LID) Cleared 10/22/2024 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 1/23/2025 DARIN LAM
Sewer availability Cleared 1/23/2025 DARIN LAM
Roof/Waste drainage to street Cleared 1/27/2025 DARIN LAM
Encroachment in public way Cleared 1/29/2025 SAUL GARCIA
Coastal Zone Cleared 5/12/2025 DALIA MOKAYED
GPI Written Notices Cleared 5/28/2025 DANIEL YIP
Grading Pre-Inspection Cleared 5/28/2025 DANIEL YIP

Contact Information

Contractor Owner-Builder       ,
Engineer Golabtounkar,, Tony Hamid; Lic. No.: C49104 1434 WESTWOOD BLVD ST 17      LOS ANGELES, CA 90024
Engineer Jung,, Jason; Lic. No.: C80569 1032 PALM AVE      SAN GABRIEL, CA 91776

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/28/2025 Partial Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 9/19/2025 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 9/19/2025 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 10/8/2025 Partial Approval STEPHANIE SWANSON
Underground Mechanical 10/8/2025 Partial Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 10/21/2025 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 10/21/2025 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 11/4/2025 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 11/4/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 12/15/2025 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 2/17/2026 Conditional Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 2/25/2026 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 2/25/2026 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 3/23/2026 Approved STEPHANIE SWANSON
PLUMBING-Rough 3/24/2026 Partial Approval STEPHANIE SWANSON
Underground Mechanical 3/24/2026 Approved STEPHANIE SWANSON
HVAC-Rough 5/19/2026 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 5/27/2026 Approved Pending GreenApproval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 5/27/2026 Partial Approval STEPHANIE SWANSON
Verify Sprinkler Sign Off 5/27/2026 Approved STEPHANIE SWANSON