227 N CORONADO ST 90026
Certificate Information: 227 N CORONADO ST 90026
- Application / Permit
- 24014-10000-04343
- Plan Check / Job No.
- B24LA24544
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert Existing Garage into ADU with small addition. Remove existing patio attached to garage.
- Permit Issued
- Issued on 4/8/2025
- Issuing Office
- Current Status
- CofO Issued on 1/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2024 | RICARDO RAMIREZ |
| Corrections Issued | 10/23/2024 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 1/24/2025 | ADAM HEGAZI |
| Applicant returned to address corrections | 1/29/2025 | ADAM HEGAZI |
| Plan Check Approved | 2/20/2025 | ADAM HEGAZI |
| Issued | 4/8/2025 | APPLICANT |
| CofO in Progress | 1/8/2026 | FREDDIE RIVERA |
| Permit Finaled | 1/9/2026 | DEROLD HAUFF |
| CofO Issued | 1/9/2026 | DEROLD HAUFF |
| Permit Finaled | 1/9/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/22/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 11/22/2024 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 12/31/2024 | MICHAEL TEMPLE |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2025 | CELINA MORENO |
| Sewer availability | Cleared | 1/8/2025 | CELINA MORENO |
| Construction near power lines | Cleared | 1/15/2025 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 1/26/2025 | RICARDO RAMIREZ |
Contact Information
| Architect | , ; Lic. No.: C36724 | , |
| Contractor | Owner-Builder | , |
| Engineer | Gao,, Jianfeng; Lic. No.: NA88478 | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/28/2025 | Corrections Issued | FREDDIE RIVERA |
| METHANE-Subgrade | 6/16/2025 | Approved | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 6/23/2025 | Conditional Approval | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 6/24/2025 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/25/2025 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 6/25/2025 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 6/25/2025 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Final | 7/18/2025 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 7/18/2025 | Corrections Issued | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2025 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 8/13/2025 | Conditional Approval | FREDDIE RIVERA |
| HVAC-Rough | 8/13/2025 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Final | 8/13/2025 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 8/19/2025 | Conditional Approval | FREDDIE RIVERA |
| Green Building Rough | 8/19/2025 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 8/19/2025 | Partial Approval | FREDDIE RIVERA |
| METHANE-Rough | 8/19/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 8/19/2025 | Approved | FREDDIE RIVERA |
| Insulation | 8/21/2025 | Corrections Issued | ALEX COLIN |
| Insulation | 8/26/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 8/28/2025 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 8/28/2025 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 9/30/2025 | Approved | DEVON JACKSON |
| BUILDING-Rough-Frame | 10/17/2025 | No Access for Inspection | FREDDIE RIVERA |
| Final | 10/17/2025 | No Access for Inspection | FREDDIE RIVERA |
| Green Building Final | 10/17/2025 | No Access for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/17/2025 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 10/17/2025 | No Access for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/23/2025 | Approved | FREDDIE RIVERA |
| Final | 10/23/2025 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 10/23/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/23/2025 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 10/23/2025 | Corrections Issued | FREDDIE RIVERA |
| Final | 11/7/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/7/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 11/13/2025 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 11/13/2025 | Corrections Issued | FREDDIE RIVERA |
| Final | 12/29/2025 | OK to Issue CofO | FREDDIE RIVERA |
| Smoke Detectors | 12/29/2025 | Approved | FREDDIE RIVERA |