6624 S HAAS AVE 90047

Certificate Information: 6624 S HAAS AVE 90047

Application / Permit
24014-10000-04339
Plan Check / Job No.
B24LA24513
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERT (E) DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)-(d).
Permit Issued
Issued on 1/23/2025
Issuing Office
Current Status
CofO Issued on 6/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2024 APPLICANT
Assigned to Plan Check Engineer 9/30/2024 GIOVANNY CHAVEZ
Corrections Issued 10/1/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 12/6/2024 OMAR GARNICA
Applicant returned to address corrections 12/11/2024 PINANK PATEL
Plan Check Approved 12/20/2024 PINANK PATEL
Issued 1/23/2025 APPLICANT
CofO in Progress 6/9/2025 BARRY HACHE
Permit Finaled 6/11/2025 DEROLD HAUFF
CofO Issued 6/11/2025 DEROLD HAUFF
Permit Finaled 6/11/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/4/2024 JEANIE LAM
Roof/Waste drainage to street Cleared 10/4/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/15/2024 JEANIE LAM
Sewer availability Cleared 11/15/2024 JEANIE LAM
Construction near power lines Cleared 12/18/2024 RIDWAN HARDY
Construction within easement Cleared 12/18/2024 RIDWAN HARDY

Contact Information

Contractor Tech Master Construction Inc; Lic. No.: 1054601-B       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 2/3/2025 Approved BARRY HACHE
Deputy Drilled-In Anchors 2/5/2025 Conditional Approval BARRY HACHE
Footing/Foundation/Slab 2/10/2025 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 2/19/2025 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 2/20/2025 Conditional Approval SCOTT FINNILA
Underground Mechanical 2/20/2025 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Partial Approval OSVALDO PARAMO
Sewer 3/7/2025 Approved ANTHONY RAMOS
Underground Mechanical 3/7/2025 Approved ANTHONY RAMOS
Green Building Rough 3/10/2025 Not Ready for Inspection BARRY HACHE
Rough-Elec/Plmb/HVAC 3/10/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 3/12/2025 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 3/12/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 3/14/2025 Not Ready for Inspection BARRY HACHE
Green Building Rough 3/14/2025 Not Ready for Inspection BARRY HACHE
Shower Pan 3/14/2025 Approved BARRY HACHE
BUILDING-Rough-Frame 3/17/2025 Approved ENRIQUE MIRELES
Green Building Rough 3/17/2025 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/17/2025 Approved ENRIQUE MIRELES
Insulation 3/21/2025 Corrections Issued JOSH MEISTER
Insulation 4/7/2025 Approved BARRY HACHE
Drywall Nailing 4/11/2025 Approved BARRY HACHE
Underground Mechanical 5/7/2025 Approved BARRY HACHE
Final 5/19/2025 Corrections Issued BARRY HACHE
Footing/Foundation/Slab 5/19/2025 Approved BARRY HACHE
Green Building Final 5/19/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 5/19/2025 SGSOV Not Ready BARRY HACHE
Service/Power Release 5/19/2025 Not Ready for Inspection BARRY HACHE
Smoke Detectors 5/19/2025 Approved BARRY HACHE
Final 5/23/2025 Corrections Issued BARRY HACHE
Green Building Final 5/23/2025 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 5/23/2025 SGSOV Not Ready BARRY HACHE
Service/Power Release 5/23/2025 Not Ready for Inspection BARRY HACHE
Final 6/2/2025 Not Ready for Inspection BARRY HACHE
Green Building Final 6/2/2025 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 6/2/2025 SGSOV Approved BARRY HACHE
Final 6/6/2025 OK to Issue CofO BARRY HACHE
Green Building Final 6/6/2025 Approved BARRY HACHE
Service/Power Release 6/6/2025 Approved BARRY HACHE