10610 1/4 S WEIGAND AVE 90002
Certificate Information: 10610 1/4 S WEIGAND AVE 90002
- Application / Permit
- 24014-10000-04335
- Plan Check / Job No.
- B24LA24488
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EpLAN: Supplemental ref: 20014-70000-00655 Increase scope of work to make an addition (759 sf) to main dwelling and convert portion of existing dwelling to JADU (489 sf).
- Permit Issued
- Issued on 3/26/2025
- Issuing Office
- Current Status
- Issued on 3/26/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | RICARDO RAMIREZ |
| Corrections Issued | 10/12/2024 | RICARDO RAMIREZ |
| Quality Review Completed | 11/21/2024 | HERNAN ARREOLA |
| Applicant returned to address corrections | 1/24/2025 | RICARDO RAMIREZ |
| Plan Check Approved | 3/25/2025 | RICARDO RAMIREZ |
| Issued | 3/26/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/12/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2024 | WALLIE JONG |
| Low Impact Development (LID) | Cleared | 12/17/2024 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 1/17/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 1/27/2025 | TREVOR QUAN |
Contact Information
| Contractor | Mj Development Real Estate & Construction Llc; Lic. No.: 1107236-B | , |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Smoke Detectors | 7/29/2026 |
| Final | 7/29/2026 |
Inspection Request History
| Footing/Foundation/Slab | 4/23/2025 | Partial Inspection | KEITH EDGHILL |
| Footing/Foundation/Slab | 4/29/2025 | Conditional Approval | KEITH EDGHILL |
| BUILDING-Rough-Frame | 6/11/2025 | Approved | KEITH EDGHILL |
| ELECTRICAL-Rough | 6/11/2025 | Approved | KEITH EDGHILL |
| PLUMBING-Rough | 6/11/2025 | Approved | KEITH EDGHILL |
| Insulation | 9/12/2025 | Approved | KEITH EDGHILL |
| Drywall Nailing | 10/2/2025 | Partial Approval | KEITH EDGHILL |
| Drywall Nailing | 10/7/2025 | Not Ready for Inspection | KEITH EDGHILL |
| Drywall Nailing | 10/22/2025 | Conditional Approval | KEITH EDGHILL |
| Final | 2/24/2026 | Not Ready for Inspection | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Not Ready | KEITH EDGHILL |
| Final | 4/15/2026 | Not Ready for Inspection | KEITH EDGHILL |
| Footing/Foundation/Slab | 4/15/2026 | Approved | KEITH EDGHILL |
| SGSOV-Seismic Gas S/O Valve | 4/15/2026 | SGSOV Approved | KEITH EDGHILL |
| Smoke Detectors | 4/15/2026 | Partial Approval | KEITH EDGHILL |
| Final | 7/9/2026 | Not Ready for Inspection | KEITH EDGHILL |