9219-9221 W ROBIN DR 90069

Certificate Information: 9219-9221 W ROBIN DR 90069

Application / Permit
24014-10000-04334
Plan Check / Job No.
B24LA24479
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY ADDITION TO (E) TWO-STORY SINGLE FAMILY RESIDENCE WITH ATTACHED CARPORT REMOVE (E) ATTACHED 2 CAR CARPORT ADDITION TO INCLUDE ATTACHED 2-CAR GARAGE AND (N) ATTACHED ADU ON SECOND FLOOR ADU PER LAMC 12.22 A.33(c) AND (e)
Permit Issued
Issued on 3/6/2025
Issuing Office
Current Status
CofO Issued on 1/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 JAD BASMA
Corrections Issued 9/28/2024 JAD BASMA
Quality Review Completed 9/30/2024 GARO TELMI
Plan Check Approved 3/6/2025 JAD BASMA
Issued 3/6/2025 APPLICANT
CofO in Progress 12/22/2025 ROY SPAULDING
No Progress 12/23/2025 DEROLD HAUFF
CofO in Progress 12/23/2025 DEROLD HAUFF
Permit Finaled 1/8/2026 DEROLD HAUFF
Permit Finaled 1/8/2026 DEROLD HAUFF
CofO Issued 1/8/2026 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/18/2024 JESSICA OPINION
BHO/Hillside ordinance Cleared 10/18/2024 JESSICA OPINION
BHO/Hillside ordinance Cleared 10/18/2024 JESSICA OPINION
BHO/Hillside ordinance Cleared 10/18/2024 JESSICA OPINION
BHO/Hillside ordinance Cleared 10/18/2024 JESSICA OPINION
Street Frontage Cleared 10/18/2024 JESSICA OPINION
Address approval Cleared 11/7/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 11/7/2024 JUSTIN BICOL
ZA Case Cleared 11/14/2024 MAYELA VILLA
Eng Process Fee Ord 176,300 Cleared 11/15/2024 JUSTIN BICOL
Sewer availability Cleared 11/15/2024 JUSTIN BICOL
Hydrant and Access approval Cleared 2/11/2025 PATRICK PEREZ
GPI Written Notices Cleared 3/5/2025 JAD BASMA
Grading Pre-Inspection Cleared 3/5/2025 JAD BASMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/12/2025 Approved ROY SPAULDING
PLUMBING-Rough 4/11/2025 Approved DAVID WILLIAMS
Underground Mechanical 4/11/2025 Approved DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 4/15/2025 Approved ROY SPAULDING
Footing/Foundation/Slab 4/15/2025 Partial Approval ROY SPAULDING
Reinforced Concrete Frame 4/18/2025 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 5/2/2025 Partial Approval CRAIG VAUGHAN
Deputy Wood Construction 5/16/2025 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/16/2025 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 5/27/2025 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 5/27/2025 Partial Approval BRIAN SULLIVAN
HVAC-Rough 5/27/2025 Corrections Issued BRIAN SULLIVAN
PLUMBING-Rough 5/27/2025 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 5/28/2025 Not Ready for Inspection ROY SPAULDING
ELECTRICAL-Rough 6/2/2025 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 6/5/2025 Approved BRIAN SULLIVAN
Green Building Rough 6/5/2025 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 6/5/2025 Not Ready for Inspection BRIAN SULLIVAN
Interior/Exterior Lathing 6/6/2025 Partial Approval ROY SPAULDING
Insulation 6/9/2025 Approved BRENDAN MORELLI
Drywall Nailing 6/12/2025 Approved BRENDAN MORELLI
Shower Pan 6/25/2025 Approved JOSH MEISTER
Interior/Exterior Lathing 6/27/2025 Approved JOSH MEISTER
ELECTRICAL-Final 10/9/2025 Approved ROY SPAULDING
Final 10/9/2025 Corrections Issued ROY SPAULDING
Footing/Foundation/Slab 10/9/2025 Approved ROY SPAULDING
Green Building Final 10/9/2025 Approved ROY SPAULDING
HVAC-Final 10/9/2025 Approved ROY SPAULDING
PLUMBING-Final 10/9/2025 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Approved ROY SPAULDING
Smoke Detectors 10/9/2025 Approved ROY SPAULDING
Final 11/13/2025 Corrections Issued ROY SPAULDING
Final 12/19/2025 OK to Issue CofO ROY SPAULDING