14170 W CHANDLER BLVD 91401

Certificate Information: 14170 W CHANDLER BLVD 91401

Application / Permit
24014-10000-04322
Plan Check / Job No.
B24LA24319
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
[ePlan] Front addition to existing 2-story SFD for new attached cabana and garage.
Permit Issued
Issued on 5/20/2025
Issuing Office
Current Status
Issued on 5/20/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/25/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 MAHNAZ NOURHASHEMI
Corrections Issued 9/29/2024 MAHNAZ NOURHASHEMI
Quality Review Completed 10/8/2024 TU HUA
Plan Check Approved 4/23/2025 MAHNAZ NOURHASHEMI
Issued 5/20/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/12/2024 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 10/16/2024 BRYAN GODINEZ
ZA Case Cleared 10/23/2024 DORIAN AGUILAR
ZA Case Cleared 10/23/2024 DORIAN AGUILAR
Trees in Parkway Cleared 2/20/2025 BRANDON WONG
Permit Cleared 2/21/2025 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/11/2025 Approved RYAN SALAZAR
Deputy Reinf. Concrete 8/12/2025 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/16/2025 Approved RYAN SALAZAR
ELECTRICAL-Rough 9/16/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/8/2025 Not Ready for Inspection WAYNE REGESTER
Interior/Exterior Lathing 10/8/2025 Approved WAYNE REGESTER
Final 12/5/2025 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 12/5/2025 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 12/5/2025 Not Ready for Inspection MISAEL ESPARZA
Pre-Inspection 12/12/2025 Partial Inspection RYAN SALAZAR