1782 N VIEWMONT DR 90069
Certificate Information: 1782 N VIEWMONT DR 90069
- Application / Permit
- 24014-10000-04314
- Plan Check / Job No.
- B24LA24284
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Addition and remodel of existing hillside single family dwelling. INCLOSURE OF BALCONY ON 2ND AND 3RD STORY AND CONVERSION OF UN HABITABLE SPACE ON THE GROUND FLOOR TO BE PART OF THE (E) SFD.
- Permit Issued
- Issued on 12/16/2024
- Issuing Office
- Current Status
- CofO Issued on 8/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2024 | VARAND SARKISIAN |
| Corrections Issued | 9/30/2024 | VARAND SARKISIAN |
| Quality Review Completed | 10/4/2024 | GARO TELMI |
| Applicant returned to address corrections | 11/21/2024 | VARAND SARKISIAN |
| Plan Check Approved | 12/13/2024 | VARAND SARKISIAN |
| Issued | 12/16/2024 | APPLICANT |
| CofO in Progress | 7/31/2025 | BRIAN SULLIVAN |
| Permit Finaled | 8/1/2025 | DEROLD HAUFF |
| CofO Issued | 8/1/2025 | DEROLD HAUFF |
| Permit Finaled | 8/1/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/1/2024 | DAVID LOPEZ |
| BHO/Hillside ordinance | Cleared | 10/1/2024 | DAVID LOPEZ |
| BHO/Hillside ordinance | Cleared | 10/1/2024 | DAVID LOPEZ |
| BHO/Hillside ordinance | Cleared | 10/1/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 10/1/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 10/1/2024 | DAVID LOPEZ |
| ZI | Cleared | 10/7/2024 | ROSALINDA MEZA |
| BHO/Hillside ordinance | Cleared | 12/9/2024 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 12/13/2024 | VARAND SARKISIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: NA3141 | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 12/17/2024 | Not Ready for Inspection | ROY SPAULDING |
| HVAC-Rough | 12/17/2024 | Not Ready for Inspection | ROY SPAULDING |
| Insulation | 12/17/2024 | Not Ready for Inspection | ROY SPAULDING |
| Interior/Exterior Lathing | 12/17/2024 | Corrections Issued | ROY SPAULDING |
| PLUMBING-Rough | 12/17/2024 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 12/19/2024 | Approved | ROY SPAULDING |
| HVAC-Rough | 12/19/2024 | Approved | ROY SPAULDING |
| Insulation | 12/19/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 12/19/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 12/19/2024 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2025 | Not Ready for Inspection | ROY SPAULDING |
| Deputy Wood Construction | 1/7/2025 | Conditional Approval | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2025 | Approved | ROY SPAULDING |
| Drywall Nailing | 1/17/2025 | Approved | ROY SPAULDING |
| Shower Pan | 1/24/2025 | Approved | ROY SPAULDING |
| Deputy Drilled-In Anchors | 1/30/2025 | Conditional Approval | ROY SPAULDING |
| Footing/Foundation/Slab | 2/3/2025 | Corrections Issued | ROY SPAULDING |
| Interior/Exterior Lathing | 2/3/2025 | Not Ready for Inspection | ROY SPAULDING |
| Footing/Foundation/Slab | 2/5/2025 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 4/11/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 4/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 4/11/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/11/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 4/11/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 4/16/2025 | Corrections Issued | ROY SPAULDING |
| Green Building Final | 4/16/2025 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 4/16/2025 | SGSOV Not Ready | ROY SPAULDING |
| Smoke Detectors | 4/16/2025 | Approved | ROY SPAULDING |
| Final | 4/22/2025 | Corrections Issued | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 4/22/2025 | SGSOV No Gas | ROY SPAULDING |
| Final | 7/30/2025 | OK to Issue CofO | BRIAN SULLIVAN |