8230 N QUARTZ AVE 91306
Certificate Information: 8230 N QUARTZ AVE 91306
- Application / Permit
- 24014-10000-04298
- Plan Check / Job No.
- B24VN15105
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- convert garage to ADU and addition
- Permit Issued
- Issued on 5/8/2025
- Issuing Office
- Current Status
- Issued on 5/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 9/21/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 9/30/2024 | YOUNG KIM |
| Plan Check Approved | 4/13/2025 | ARSALAN SHABESTARI |
| Issued | 5/8/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/14/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 11/14/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/27/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 11/27/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/2/2025 | Partial Approval | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 9/19/2025 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 9/22/2025 | Approved | ALEXANDER HANDY |
| Deputy Wood Construction | 10/2/2025 | Conditional Approval | HENRY KIM |
| Deputy Wood Construction | 10/3/2025 | Conditional Approval | HENRY KIM |
| Deputy Wood Construction | 1/12/2026 | Conditional Approval | HENRY KIM |
| ELECTRICAL-Rough | 1/12/2026 | Approved | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2026 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 1/12/2026 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 1/12/2026 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 1/12/2026 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 1/15/2026 | Approved | ALEXANDER HANDY |
| Green Building Rough | 1/15/2026 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 1/15/2026 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 1/23/2026 | Partial Approval | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 2/6/2026 | Approved | DAVID FASTIGGI |
| Insulation | 2/10/2026 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 2/23/2026 | Approved | DAVID FASTIGGI |