17957-17959 W COHASSET ST 91335
Certificate Information: 17957-17959 W COHASSET ST 91335
- Application / Permit
- 24014-10000-04276
- Plan Check / Job No.
- B24LA23963
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW ATTACHED UNIT PER SB9 TWO UNIT DEVELOPMENT TO EXISTING 1-STORY, SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. RESULT IS TWO-STORY DUPLEX. NEW LAUNDRY ROOM WILL BE ADDED TO (E) SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 3/3/2025
- Issuing Office
- Current Status
- CofO Issued on 4/25/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | JESSE VIDUYA |
| Corrections Issued | 10/8/2024 | JESSE VIDUYA |
| Quality Review Completed | 10/15/2024 | CHAD DOI |
| Applicant returned to address corrections | 2/12/2025 | JESSE VIDUYA |
| Applicant returned to address corrections | 2/26/2025 | JESSE VIDUYA |
| Plan Check Approved | 2/28/2025 | JESSE VIDUYA |
| Issued | 3/3/2025 | APPLICANT |
| CofO in Progress | 1/17/2026 | ARUTYUN MADATYAN |
| Permit Finaled | 4/25/2026 | MICHAEL PELHAM |
| CofO Issued | 4/25/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/25/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 10/16/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 10/16/2024 | CARLOS RAMIREZ |
| Grading Pre-Inspection | Cleared | 10/16/2024 | CHARLES POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 10/22/2024 | CARLOS RAMIREZ |
| Hold | Cleared | 11/20/2024 | ALEXIS SCHULTZ |
| Senate Bill 9 | Cleared | 11/21/2024 | DORIAN AGUILAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barragan,, Pedro; Lic. No.: C90531 | 329 N HUBBARD AVE SAN FERNANDO, CA 91340 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/7/2025 | Corrections Issued | ARUTYUN MADATYAN |
| PLUMBING-Rough | 4/4/2025 | Partial Approval | ARUTYUN MADATYAN |
| Deputy Drilled-In Anchors | 4/14/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 4/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Gas Test | 4/14/2025 | No Access for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 4/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Sewer | 4/14/2025 | Approved | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 4/18/2025 | Partial Approval | JUAN ALVARADO |
| Gas Test | 4/18/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 4/18/2025 | Partial Approval | JUAN ALVARADO |
| Sewer | 4/18/2025 | Approved | JUAN ALVARADO |
| Deputy Drilled-In Anchors | 4/22/2025 | Conditional Approval | ROBERT GOLD |
| Deputy Drilled-In Anchors | 4/23/2025 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Corrections Issued | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2025 | Partial Approval | JUAN ALVARADO |
| PLUMBING-Rough | 5/21/2025 | Partial Approval | JUAN ALVARADO |
| Pre-Inspection | 6/12/2025 | Corrections Issued | JUAN ALVARADO |
| Deputy Drilled-In Anchors | 7/17/2025 | Conditional Approval | ROBERT GOLD |
| Insulation | 8/22/2025 | Approved | JUAN ALVARADO |
| Drywall Nailing | 8/26/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 8/26/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 8/26/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 9/3/2025 | Approved | JUAN ALVARADO |
| Pre-Inspection | 10/16/2025 | Not Ready for Inspection | JUAN ALVARADO |
| BUILDING-Rough-Frame | 1/5/2026 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 1/5/2026 | Not Ready for Inspection | JUAN ALVARADO |
| Final | 1/5/2026 | Corrections Issued | JUAN ALVARADO |
| Footing/Foundation/Slab | 1/5/2026 | Approved | JUAN ALVARADO |
| Green Building Final | 1/5/2026 | Approved | JUAN ALVARADO |
| HVAC-Final | 1/5/2026 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 1/5/2026 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 1/5/2026 | SGSOV Approved | JUAN ALVARADO |
| Smoke Detectors | 1/5/2026 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 1/16/2026 | Approved | ARUTYUN MADATYAN |
| Final | 1/16/2026 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 1/16/2026 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 1/16/2026 | Approved | ARUTYUN MADATYAN |