8003 N WYNNE AVE 91335

Certificate Information: 8003 N WYNNE AVE 91335

Application / Permit
24014-10000-04268
Plan Check / Job No.
B24LA23890
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: Convert (E) Detached 1-Story Garage to ADU w/ Ground Floor Addition per LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 1/4/2025
Issuing Office
Current Status
CofO Issued on 9/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2024 APPLICANT
Assigned to Plan Check Engineer 9/25/2024 DAVID CASTILLO
Corrections Issued 9/26/2024 DAVID CASTILLO
Applicant returned to address corrections 12/24/2024 DAVID CASTILLO
Plan Check Approved 1/1/2025 DAVID CASTILLO
Issued 1/4/2025 APPLICANT
CofO in Progress 9/12/2025 ARUTYUN MADATYAN
Permit Finaled 9/30/2025 MICHAEL PELHAM
CofO Issued 9/30/2025 MICHAEL PELHAM
Permit Finaled 9/30/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 10/8/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 10/8/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 10/8/2024 BIAINA HARITUNIAN
Sewer availability Cleared 10/8/2024 BIAINA HARITUNIAN
Construction within easement Cleared 12/26/2024 RIDWAN HARDY
Grading Pre-Inspection Cleared 12/31/2024 DAVID CASTILLO

Contact Information

Contractor Ion Builders Inc; Lic. No.: 1069085-B 6615 CHIMINEAS AVENUE      RESEDA, CA 91335
Engineer Mniarji,, Majd Sameer; Lic. No.: C93049 7812 VASSAR AVENUE      CANOGA PARK, CA 91304

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/7/2025 Approved ARUTYUN MADATYAN
Sewer 1/7/2025 Approved ARUTYUN MADATYAN
Underground Mechanical 1/7/2025 Approved ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 1/16/2025 Corrections Issued ARUTYUN MADATYAN
Footing/Foundation/Slab 1/17/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 2/10/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Rough 3/7/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Partial Approval ARUTYUN MADATYAN
Green Building Rough 3/7/2025 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Rough 3/7/2025 Corrections Issued ARUTYUN MADATYAN
PLUMBING-Rough 3/7/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 3/11/2025 Approved ARUTYUN MADATYAN
Green Building Rough 3/11/2025 Approved ARUTYUN MADATYAN
HVAC-Rough 3/11/2025 Approved ARUTYUN MADATYAN
Insulation 3/19/2025 Approved ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 3/24/2025 Approved ARUTYUN MADATYAN
Shower Pan 3/24/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 3/26/2025 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 3/26/2025 Approved ARUTYUN MADATYAN
Final 9/8/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 9/8/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 9/8/2025 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 9/8/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 9/12/2025 Approved ARUTYUN MADATYAN
Final 9/12/2025 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 9/12/2025 Approved ARUTYUN MADATYAN
HVAC-Final 9/12/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 9/12/2025 Approved ARUTYUN MADATYAN
Service/Power Release 9/12/2025 Approved ARUTYUN MADATYAN