4830 S VAN NESS AVE 90062
Certificate Information: 4830 S VAN NESS AVE 90062
- Application / Permit
- 24014-10000-04264
- Plan Check / Job No.
- B24LA23836
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: New irregular shaped addition of 22' 6" x 23' to detached garage to create a 22' 6" x 23' ADU per LAMC 12.22 A.33(b)(1)3. All work per engineer.
- Permit Issued
- Issued on 5/1/2025
- Issuing Office
- Current Status
- CofO Issued on 3/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 9/30/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 1/16/2025 | DANIEL ABRAMYAN |
| Plan Check Approved | 2/5/2025 | NAREG ATARIAN |
| Issued | 5/1/2025 | APPLICANT |
| CofO in Progress | 3/13/2026 | SABAS ALONSO |
| Permit Finaled | 3/13/2026 | DEROLD HAUFF |
| CofO Issued | 3/13/2026 | DEROLD HAUFF |
| Permit Finaled | 3/13/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/24/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 12/24/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 12/30/2024 | JUSTIN BICOL |
| Construction near power lines | Cleared | 1/8/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Dhs Ventures Inc; Lic. No.: 1047699-B | , |
| Contractor | La Ccs; Lic. No.: 1047699-B | , |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | 1250 W GLENOAKS BLVD E355 GLENDALE, CA 91201 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/8/2025 | Approved | MICHAEL LEWIS |
| Pre-Inspection | 5/19/2025 | Partial Inspection | SABAS ALONSO |
| PLUMBING-Rough | 6/3/2025 | Corrections Issued | JOHN QUINTANILLA |
| Deputy Drilled-In Anchors | 6/9/2025 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 6/9/2025 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 6/11/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Rough | 6/11/2025 | Approved | LUIS CASTRO |
| Footing/Foundation/Slab | 6/12/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 8/8/2025 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 8/8/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2025 | Approved | BARRY HACHE |
| Green Building Rough | 8/25/2025 | Not Ready for Inspection | BARRY HACHE |
| Shower Pan | 8/25/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 8/29/2025 | Partial Approval | BARRY HACHE |
| Pre-Inspection | 10/7/2025 | Partial Inspection | SABAS ALONSO |
| Service/Power Release | 10/10/2025 | Conditional Approval | SABAS ALONSO |
| Underground Mechanical | 10/10/2025 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/20/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 10/20/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 10/20/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 10/20/2025 | Approved | SABAS ALONSO |
| Sewer | 10/20/2025 | Approved | SABAS ALONSO |
| Shower Pan | 10/20/2025 | Corrections Issued | SABAS ALONSO |
| Insulation | 10/22/2025 | Approved | SABAS ALONSO |
| Drywall Nailing | 10/24/2025 | Approved | ALEX COLIN |
| Green Building Rough | 10/24/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 10/24/2025 | Not Ready for Inspection | ALEX COLIN |
| Interior/Exterior Lathing | 10/27/2025 | Not Ready for Inspection | ANTHONY RAMOS |
| Interior/Exterior Lathing | 10/30/2025 | Approved | SABAS ALONSO |
| Final | 12/4/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 12/4/2025 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/4/2025 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 12/4/2025 | Approved | SABAS ALONSO |
| Final | 12/16/2025 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Approved | SABAS ALONSO |
| Final | 1/2/2026 | Not Ready for Inspection | SABAS ALONSO |
| Service/Power Release | 1/2/2026 | Approved | SABAS ALONSO |
| Final | 1/5/2026 | Corrections Issued | SABAS ALONSO |
| Final | 3/12/2026 | OK to Issue CofO | SABAS ALONSO |