2241 N CAHUENGA BLVD 90068
Certificate Information: 2241 N CAHUENGA BLVD 90068
- Application / Permit
- 24014-10000-04254
- Plan Check / Job No.
- B24LA23741
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel of single family dwelling and (N) roof top deck
- Permit Issued
- Issued on 2/28/2025
- Issuing Office
- Current Status
- Permit Finaled on 2/17/2026
Permit Application Status History
| Submitted | 9/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2024 | JESSE VIDUYA |
| Corrections Issued | 10/9/2024 | JESSE VIDUYA |
| Quality Review Completed | 10/11/2024 | KEN GILL |
| Building Plans Picked Up | 10/18/2024 | APPLICANT |
| Applicant returned to address corrections | 1/27/2025 | JESSE VIDUYA |
| Plan Check Approved | 2/20/2025 | JESSE VIDUYA |
| Issued | 2/28/2025 | APPLICANT |
| CofO in Progress | 2/4/2026 | CRAIG VAUGHAN |
| CofO in Progress | 2/4/2026 | CRAIG VAUGHAN |
| Permit Finaled | 2/13/2026 | CRAIG VAUGHAN |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/25/2024 | JUSTIN BICOL |
| BHO/Hillside ordinance | Cleared | 11/25/2024 | JUSTIN BICOL |
| BHO/Hillside ordinance | Cleared | 11/25/2024 | JUSTIN BICOL |
| BHO/Hillside ordinance | Cleared | 11/25/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 11/25/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2024 | JUSTIN BICOL |
| Highway dedication | Cleared | 12/3/2024 | CHRISTINA BRACO |
| BHO/Hillside ordinance | Cleared | 12/9/2024 | DAVID LOPEZ |
| Construction within easement | Cleared | 12/12/2024 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 2/4/2025 | RUEL COLE |
Contact Information
| Contractor | California Designers Remodeling Inc; Lic. No.: 946160-B | 22567 MARGARITA DRIVE WOODLAND HILLS, CA 91364 |
| Engineer | Moayedi,, Kamran; Lic. No.: C35137 | 26180 ENTERPRISE WY STE 300 LAKE FOREST, CA 92630 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/17/2025 | No Access for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/21/2025 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 5/1/2025 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/27/2025 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 5/27/2025 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 5/27/2025 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 5/27/2025 | Corrections Issued | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 5/27/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| MERV13>=Rough | 5/27/2025 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/27/2025 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 5/30/2025 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 5/30/2025 | Approved | CRAIG VAUGHAN |
| Insulation | 5/30/2025 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 6/18/2025 | Approved | CRAIG VAUGHAN |
| Shower Pan | 6/18/2025 | Approved | CRAIG VAUGHAN |
| Special/Order Compliance | 8/15/2025 | Partial Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/17/2025 | Approved | CRAIG VAUGHAN |
| Final | 11/17/2025 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 11/17/2025 | Approved | CRAIG VAUGHAN |
| MERV13>=Final | 11/17/2025 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/17/2025 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 11/17/2025 | Approved | CRAIG VAUGHAN |
| Final | 11/19/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 1/30/2026 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 2/5/2026 | Corrections Issued | CRAIG VAUGHAN |
| Final | 2/13/2026 | Permit Finaled | CRAIG VAUGHAN |