2272 S OVERLAND AVE 90064

Certificate Information: 2272 S OVERLAND AVE 90064

Application / Permit
24014-10000-04231
Plan Check / Job No.
B24LA23575
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF EXISTING SINGLE FAMILY DWELLING - PER ENGINEER
Permit Issued
Issued on 12/4/2024
Issuing Office
Current Status
Permit Finaled on 6/11/2025

Permit Application Status History

Submitted 9/19/2024 APPLICANT
Assigned to Plan Check Engineer 9/25/2024 DANIEL ABRAMYAN
Corrections Issued 9/26/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 10/23/2024 DANIEL ABRAMYAN
Plan Check Approved 11/18/2024 DANIEL ABRAMYAN
Issued 12/4/2024 APPLICANT
Permit Finaled 6/10/2025 DANIEL VERA

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/6/2024 LANNY MERRICK

Contact Information

Architect Davis,, Paul S; Lic. No.: NA27920       ,
Contractor Gaga Builders Inc; Lic. No.: 1038675-B       ,
Engineer Phillips,, Craig; Lic. No.: NA69673       ,

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/14/2025 Corrections Issued STEPHANIE SWANSON
Deputy Drilled-In Anchors 1/15/2025 Approved STEPHANIE SWANSON
Footing/Foundation/Slab 1/15/2025 Approved STEPHANIE SWANSON
Deputy Drilled-In Anchors 1/27/2025 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 1/29/2025 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 2/19/2025 Conditional Approval STEPHANIE SWANSON
Rough-Elec/Plmb/HVAC 2/19/2025 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 2/28/2025 Corrections Issued STEPHANIE SWANSON
Insulation 3/6/2025 Approved STEPHANIE SWANSON
Shower Pan 3/6/2025 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 3/11/2025 Conditional Approval DANIEL VERA
Drywall Nailing 3/13/2025 Partial Approval DANIEL VERA
Interior/Exterior Lathing 3/18/2025 Not Ready for Inspection DANIEL VERA
Deputy Wood Construction 3/19/2025 Conditional Approval DANIEL VERA
BUILDING-Rough-Frame 6/4/2025 Approved DANIEL VERA
Drywall Nailing 6/4/2025 Approved DANIEL VERA
Final 6/4/2025 Corrections Issued DANIEL VERA
METHANE-Final 6/4/2025 Approved DANIEL VERA
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Approved DANIEL VERA
Smoke Detectors 6/4/2025 Approved DANIEL VERA
Final 6/10/2025 Permit Finaled DANIEL VERA