2272 S OVERLAND AVE 90064
Certificate Information: 2272 S OVERLAND AVE 90064
- Application / Permit
- 24014-10000-04231
- Plan Check / Job No.
- B24LA23575
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL OF EXISTING SINGLE FAMILY DWELLING - PER ENGINEER
- Permit Issued
- Issued on 12/4/2024
- Issuing Office
- Current Status
- Permit Finaled on 6/11/2025
Permit Application Status History
| Submitted | 9/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 9/26/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 10/23/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 11/18/2024 | DANIEL ABRAMYAN |
| Issued | 12/4/2024 | APPLICANT |
| Permit Finaled | 6/10/2025 | DANIEL VERA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/6/2024 | LANNY MERRICK |
Contact Information
| Architect | Davis,, Paul S; Lic. No.: NA27920 | , |
| Contractor | Gaga Builders Inc; Lic. No.: 1038675-B | , |
| Engineer | Phillips,, Craig; Lic. No.: NA69673 | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/14/2025 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 1/15/2025 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 1/15/2025 | Approved | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 1/27/2025 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 1/29/2025 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 2/19/2025 | Conditional Approval | STEPHANIE SWANSON |
| Rough-Elec/Plmb/HVAC | 2/19/2025 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 2/28/2025 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 3/6/2025 | Approved | STEPHANIE SWANSON |
| Shower Pan | 3/6/2025 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 3/11/2025 | Conditional Approval | DANIEL VERA |
| Drywall Nailing | 3/13/2025 | Partial Approval | DANIEL VERA |
| Interior/Exterior Lathing | 3/18/2025 | Not Ready for Inspection | DANIEL VERA |
| Deputy Wood Construction | 3/19/2025 | Conditional Approval | DANIEL VERA |
| BUILDING-Rough-Frame | 6/4/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 6/4/2025 | Approved | DANIEL VERA |
| Final | 6/4/2025 | Corrections Issued | DANIEL VERA |
| METHANE-Final | 6/4/2025 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 6/4/2025 | SGSOV Approved | DANIEL VERA |
| Smoke Detectors | 6/4/2025 | Approved | DANIEL VERA |
| Final | 6/10/2025 | Permit Finaled | DANIEL VERA |