1537 N BANNING BLVD 90744

Certificate Information: 1537 N BANNING BLVD 90744

Application / Permit
24014-10000-04223
Plan Check / Job No.
B24LA23503
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN New 723 SF ADU addition added and built over Existing Garage with New exterior uncovered staircase.
Permit Issued
Issued on 2/13/2025
Issuing Office
Current Status
Issued on 2/13/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/20/2024 APPLICANT
Assigned to Plan Check Engineer 10/3/2024 RACHEL BEYENE
Corrections Issued 10/4/2024 RACHEL BEYENE
Quality Review Completed 10/15/2024 PRANITA SHAH
Applicant returned to address corrections 1/23/2025 RACHEL BEYENE
Plan Check Approved 2/11/2025 RAHEL BEYENE
Plan Check Approved 2/13/2025 RAHEL BEYENE
Issued 2/13/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/29/2025 ERIK BEASLEY
Roof/Waste drainage to street Cleared 1/29/2025 ERIK BEASLEY
ZI Cleared 1/29/2025 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 1/31/2025 JILVER MAZARIEGOS
Sewer availability Cleared 1/31/2025 JILVER MAZARIEGOS

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: NA76372       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/7/2025 Approved EUGENE CASSIDY
METHANE-Barrier 4/7/2025 Approved EUGENE CASSIDY
METHANE-Subgrade 4/7/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 6/11/2025 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 6/11/2025 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Partial Approval EUGENE CASSIDY
Green Building Rough 6/11/2025 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 6/11/2025 Approved EUGENE CASSIDY
Wood Frame 6/11/2025 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 11/6/2025 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 11/6/2025 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 11/6/2025 Corrections Issued EUGENE CASSIDY
Sewer 11/6/2025 Approved EUGENE CASSIDY
Wood Frame 11/6/2025 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 12/29/2025 Conditional Approval JOSEPH MCGARRY
ELECTRICAL-Rough 12/29/2025 Approved JOSEPH MCGARRY
Green Building Rough 12/29/2025 Approved JOSEPH MCGARRY
HVAC-Rough 12/29/2025 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 12/29/2025 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 12/29/2025 Approved JOSEPH MCGARRY
Shower Pan 12/29/2025 Approved JOSEPH MCGARRY
Insulation 4/9/2026 Approved EUGENE CASSIDY
Interior/Exterior Lathing 4/9/2026 Approved EUGENE CASSIDY
Drywall Nailing 5/20/2026 Conditional Approval JOSEPH MCGARRY
Interior/Exterior Lathing 5/20/2026 Approved JOSEPH MCGARRY
Special/Order Compliance 5/20/2026 Corrections Issued JOSEPH MCGARRY