1022 W OLIVER ST 90732

Certificate Information: 1022 W OLIVER ST 90732

Application / Permit
24014-10000-04221
Plan Check / Job No.
B24LA23492
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN REMOVE 91 SQFT OF FRONT PROCH. NEW 376 SF MASTER BEDROOM ADDITION WITH MASTER BATH AND WALK IN CLOSET.
Permit Issued
Issued on 12/18/2024
Issuing Office
Current Status
CofO Issued on 5/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2024 APPLICANT
Assigned to Plan Check Engineer 9/25/2024 NGHI SU
Corrections Issued 9/25/2024 NGHI SU
Applicant returned to address corrections 11/20/2024 NGHI SU
Plan Check Approved 12/4/2024 NGHI SU
Issued 12/18/2024 APPLICANT
CofO in Progress 5/21/2025 JOSEPH MCGARRY
Permit Finaled 5/22/2025 ANSON MAGLASANG
CofO Issued 5/22/2025 ANSON MAGLASANG
Permit Finaled 5/22/2025 ANSON MAGLASANG

Permit Application Clearance Information

Sewer availability Cleared 10/1/2024 XOCHITL ARQUIETA
Grading Pre-Inspection Cleared 10/6/2024 VASIL MIHALEV
Eng Process Fee Ord 176,300 Cleared 10/10/2024 XOCHITL ARQUIETA
Roof/Waste drainage to street Cleared 10/24/2024 XOCHITL ARQUIETA
Tenant Habitability Plan Cleared 11/25/2024 HUGO GARRIDO GARZA

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/16/2025 Corrections Issued BEN MOLSTAD
Excavation/Setback/Form/Re-Bar 1/21/2025 Conditional Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 1/29/2025 Partial Approval BEN MOLSTAD
Excavation/Setback/Form/Re-Bar 1/29/2025 Approved BEN MOLSTAD
Green Building Rough 1/29/2025 Not Ready for Inspection BEN MOLSTAD
Insulation 1/29/2025 Partial Approval BEN MOLSTAD
Sewer 1/29/2025 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Corrections Issued ANTHONY EGSON
Deputy Wood Construction 2/3/2025 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 3/4/2025 Partial Approval JOSEPH MCGARRY
Deputy Wood Construction 3/4/2025 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Approved JOSEPH MCGARRY
Green Building Rough 3/4/2025 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 3/4/2025 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 3/21/2025 Conditional Approval JOSEPH MCGARRY
Interior/Exterior Lathing 3/21/2025 Partial Approval JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 3/21/2025 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 4/1/2025 Approved JOSEPH MCGARRY
Green Building Rough 4/1/2025 Approved JOSEPH MCGARRY
Insulation 4/1/2025 Approved JOSEPH MCGARRY
Shower Pan 4/1/2025 Approved JOSEPH MCGARRY
Drywall Nailing 4/7/2025 Approved BEN MOLSTAD
Interior/Exterior Lathing 4/7/2025 Approved BEN MOLSTAD
Excavation/Setback/Form/Re-Bar 4/30/2025 Approved JOSEPH MCGARRY
Final 5/19/2025 Not Ready for Inspection JOHN KLARIN
Footing/Foundation/Slab 5/19/2025 Approved JOHN KLARIN
Green Building Final 5/19/2025 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 5/19/2025 SGSOV Approved JOHN KLARIN
Smoke Detectors 5/19/2025 Approved JOHN KLARIN
Final 5/21/2025 OK to Issue CofO JOSEPH MCGARRY
Green Building Final 5/21/2025 Approved JOSEPH MCGARRY