2049 S MALCOLM AVE 90025

Certificate Information: 2049 S MALCOLM AVE 90025

Application / Permit
24014-10000-04218
Plan Check / Job No.
B24LA23470
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) DETACHED GARAGE WITH ADDITION OF BATHROOM TO A NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ADD (N) STORAGE ATTACHED TO ADU. "COMPLY WITH DEPARTMENT ORDER effective date 08/22/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 1/30/2025
Issuing Office
Current Status
CofO Issued on 3/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2024 APPLICANT
Assigned to Plan Check Engineer 9/25/2024 MIROOSH KHACHATOORIAN
Corrections Issued 9/26/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 1/15/2025 ISIS ARGUETA
Plan Check Approved 1/29/2025 ISIS ARGUETA
Issued 1/30/2025 APPLICANT
CofO in Progress 1/2/2026 PETER RUBIO
Permit Finaled 3/3/2026 DANIEL SANCHEZ
CofO Issued 3/3/2026 DANIEL SANCHEZ
Permit Finaled 3/3/2026 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 9/28/2024 DARIN LAM
Roof/Waste drainage to street Cleared 9/28/2024 DARIN LAM
Specific Plan Cleared 10/1/2024 HAMID GHAEMMAGHAMI
ZA Case Cleared 10/2/2024 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 10/22/2024 DARIN LAM
Sewer availability Cleared 10/22/2024 DARIN LAM
Grading Pre-Inspection Cleared 10/28/2024 VASIL MIHALEV
Construction near power lines Cleared 12/27/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/14/2025 Approved PETER RUBIO
BUILDING-Rough-Frame 2/27/2025 Corrections Issued PETER RUBIO
Deputy Drilled-In Anchors 2/27/2025 Approved PETER RUBIO
Green Building Rough 2/27/2025 Not Ready for Inspection PETER RUBIO
METHANE-Rough 2/27/2025 Not Ready for Inspection PETER RUBIO
Footing/Foundation/Slab 3/6/2025 Approved PETER RUBIO
METHANE-Barrier 3/6/2025 Approved PETER RUBIO
METHANE-Rough 3/6/2025 Approved PETER RUBIO
METHANE-Subgrade 3/6/2025 Approved PETER RUBIO
Drywall Nailing 3/10/2025 Not Ready for Inspection PETER RUBIO
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 Not Ready for Inspection PETER RUBIO
Green Building Rough 3/10/2025 Not Ready for Inspection PETER RUBIO
Insulation 3/10/2025 Not Ready for Inspection PETER RUBIO
Drywall Nailing 3/18/2025 Approved PETER RUBIO
Green Building Rough 3/18/2025 Approved PETER RUBIO
Interior/Exterior Lathing 3/18/2025 Approved PETER RUBIO
BUILDING-Rough-Frame 7/9/2025 Approved PETER RUBIO
ELECTRICAL-Final 7/9/2025 Not Ready for Inspection PETER RUBIO
Final 7/9/2025 Not Ready for Inspection PETER RUBIO
Green Building Final 7/9/2025 Not Ready for Inspection PETER RUBIO
HVAC-Final 7/9/2025 Not Ready for Inspection PETER RUBIO
PLUMBING-Final 7/9/2025 Not Ready for Inspection PETER RUBIO
SGSOV-Seismic Gas S/O Valve 7/9/2025 SGSOV Not Ready PETER RUBIO
Smoke Detectors 7/9/2025 Approved PETER RUBIO
ELECTRICAL-Final 7/14/2025 Not Ready for Inspection PETER RUBIO
Final 7/14/2025 Corrections Issued PETER RUBIO
Green Building Final 7/14/2025 Approved PETER RUBIO
HVAC-Final 7/14/2025 Approved PETER RUBIO
PLUMBING-Final 7/14/2025 Approved PETER RUBIO
SGSOV-Seismic Gas S/O Valve 7/14/2025 SGSOV Not Ready PETER RUBIO
Final 8/13/2025 Conditional Approval PETER RUBIO
SGSOV-Seismic Gas S/O Valve 8/13/2025 SGSOV Approved PETER RUBIO
ELECTRICAL-Final 1/2/2026 Approved PETER RUBIO
Final 1/2/2026 OK to Issue CofO PETER RUBIO