3018 3/4-7/8 S 9TH AVE 90018

Certificate Information: 3018 3/4-7/8 S 9TH AVE 90018

Application / Permit
24014-10000-04184
Plan Check / Job No.
B24LA23084
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Demolish Part of the Existing Detached Garage and Construct a new 2-story building consisting of 2 New Detached ADUs.
Permit Issued
Issued on 6/27/2025
Issuing Office
Current Status
Issued on 6/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/22/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 JOE VO
Corrections Issued 9/28/2024 JOE VO
Quality Review Completed 10/1/2024 PRANITA SHAH
Plan Check Approved 2/5/2025 JOE VO
Issued 6/27/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/25/2024 JESSICA OPINION
Roof/Waste drainage to street Cleared 10/25/2024 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 11/7/2024 JESSICA OPINION
Sewer availability Cleared 11/7/2024 JESSICA OPINION
Construction near power lines Cleared 12/16/2024 RIDWAN HARDY
Hydrant and Access approval Cleared 1/15/2025 KENNETH FRASER

Contact Information

Contractor Euro Cal Construction Inc; Lic. No.: 773601-B       ,
Engineer Gupta,, Raghu; Lic. No.: C87913 6024 BUCKINGHAM PKWY UNIT 16      CULVER CITY, CA 90230

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Final 7/23/2026    Time Frame: 9-11
Special/Order Compliance 7/24/2026   

Inspection Request History

Pre-Inspection 7/10/2025 Approved JUSTIN HAWLEY
Underground Mechanical 7/24/2025 Partial Approval JUSTIN HAWLEY
Footing/Foundation/Slab 8/12/2025 Approved JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 8/19/2025 Partial Approval JUSTIN HAWLEY
Deputy Wood Construction 9/8/2025 Conditional Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 9/17/2025 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 10/6/2025 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 10/9/2025 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 10/9/2025 Approved JUSTIN HAWLEY
Insulation 11/6/2025 Conditional Approval DEVON JACKSON
Insulation 12/2/2025 Approved DEVON JACKSON
Drywall Nailing 12/11/2025 Approved JUSTIN HAWLEY
Green Building Rough 12/11/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 12/11/2025 Partial Approval JUSTIN HAWLEY
Underground Mechanical 3/10/2026 Corrections Issued JUSTIN HAWLEY
Sewer 3/24/2026 Approved JUSTIN HAWLEY
Underground Mechanical 3/24/2026 Partial Approval JUSTIN HAWLEY
Service/Power Release 5/13/2026 Corrections Issued JUSTIN HAWLEY
Service/Power Release 5/22/2026 Approved JUSTIN HAWLEY
Final 7/16/2026 Corrections Issued JUSTIN HAWLEY
Green Building Final 7/16/2026 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 7/16/2026 SGSOV Not Required JUSTIN HAWLEY
Smoke Detectors 7/16/2026 Approved JUSTIN HAWLEY