3229 S SHERBOURNE DR 1-3 90034
Certificate Information: 3229 S SHERBOURNE DR 1-3 90034
- Application / Permit
- 24014-10000-04174
- Plan Check / Job No.
- B24LA22999
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Eplan: Ground floor addition and conversion of (E) attached garage to ADU per LAMC 12.22 A.33(c) and (e) in (E) 2-Story Duplex
- Permit Issued
- Issued on 1/22/2025
- Issuing Office
- Current Status
- CofO Issued on 9/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2024 | DAVID CASTILLO |
| Corrections Issued | 9/23/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 10/2/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 10/9/2024 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 10/21/2024 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 10/26/2024 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 11/23/2024 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 12/10/2024 | AMY GUEVARRA |
| Applicant returned to address corrections | 12/16/2024 | AMY GUEVARRA |
| Plan Check Approved | 1/16/2025 | AMY GUEVARRA |
| Issued | 1/22/2025 | APPLICANT |
| CofO in Progress | 9/5/2025 | EVAN COOPER |
| Permit Finaled | 9/9/2025 | RICHARD STEINBACH |
| CofO Issued | 9/9/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/28/2024 | KORNEL LELEA |
| Address approval | Cleared | 11/21/2024 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 11/21/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 11/25/2024 | TREVOR QUAN |
| Specific Plan | Cleared | 1/13/2025 | JULISSA LOPEZ-HODOYAN |
Contact Information
| Architect | Botros,, George L; Lic. No.: C22961 | 275 CANTERBURY COURT UPLAND, CA 91784 |
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/10/2025 | Partial Approval | MEL KHACHATOURIAN |
| Underground Mechanical | 2/10/2025 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 2/28/2025 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 3/7/2025 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2025 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 4/15/2025 | No Access for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 4/15/2025 | No Access for Inspection | EVAN COOPER |
| Green Building Rough | 4/15/2025 | No Access for Inspection | EVAN COOPER |
| HVAC-Rough | 4/15/2025 | No Access for Inspection | EVAN COOPER |
| PLUMBING-Rough | 4/15/2025 | No Access for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 4/16/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 4/16/2025 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 4/16/2025 | Approved | EVAN COOPER |
| HVAC-Rough | 4/16/2025 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 4/16/2025 | Approved | EVAN COOPER |
| Service/Power Release | 4/17/2025 | Not Ready for Inspection | EVAN COOPER |
| Insulation | 4/18/2025 | Approved | EVAN COOPER |
| Drywall Nailing | 4/22/2025 | Approved | EVAN COOPER |
| Final | 5/9/2025 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 5/9/2025 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/9/2025 | SGSOV Not Ready | EVAN COOPER |
| Shower Pan | 5/9/2025 | Approved | EVAN COOPER |
| Service/Power Release | 5/20/2025 | Approved | EVAN COOPER |
| Service/Power Release | 5/22/2025 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Not Ready | EVAN COOPER |
| ELECTRICAL-Final | 9/3/2025 | Corrections Issued | EVAN COOPER |
| Final | 9/3/2025 | Corrections Issued | EVAN COOPER |
| Gas Test | 9/3/2025 | Approved | EVAN COOPER |
| HVAC-Final | 9/3/2025 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 9/3/2025 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Final | 9/5/2025 | Approved | EVAN COOPER |
| Final | 9/5/2025 | OK to Issue CofO | EVAN COOPER |
| Green Building Final | 9/5/2025 | Approved | EVAN COOPER |
| HVAC-Final | 9/5/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 9/5/2025 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 9/5/2025 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 9/5/2025 | Approved | EVAN COOPER |