16109 W DEVONSHIRE ST 91344

Certificate Information: 16109 W DEVONSHIRE ST 91344

Application / Permit
24014-10000-04154
Plan Check / Job No.
B24VN14783
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* GROUND FLOOR ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING AND INTERIOR REMODEL.
Permit Issued
Issued on 5/8/2025
Issuing Office
Current Status
Issued on 5/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/30/2024 APPLICANT
Assigned to Plan Check Engineer 9/12/2024 VIVIAN LAO
Corrections Issued 9/16/2024 VIVIAN LAO
Quality Review Completed 9/18/2024 GARO TELMI
Applicant returned to address corrections 2/28/2025 VIVIAN LAO
Applicant returned to address corrections 4/17/2025 VIVIAN LAO
Applicant returned to address corrections 4/18/2025 VIVIAN LAO
Plan Check Approved 5/7/2025 VIVIAN LAO
Issued 5/8/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/20/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 11/20/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 11/21/2024 CARLOS RAMIREZ
Sewer availability Cleared 11/21/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khansa,, Eyass; Lic. No.: C91758 2252 JOSIE AVE      LONG BEACH, CA 90815

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/11/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 7/11/2025 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Approved CHRISTOPHER ROJAS
Wood Frame 7/30/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/1/2025 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 8/1/2025 Off-Hour Fees Due
PLUMBING-Rough 8/1/2025 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/7/2025 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 8/18/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 8/28/2025 Approved RAUL OLAGI
BUILDING-Rough-Frame 9/9/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 9/9/2025 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 9/9/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 9/30/2025 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 9/30/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 9/30/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Shower Pan 10/22/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 11/10/2025 Partial Approval CHRISTOPHER MORFIN
Underground Mechanical 12/8/2025 Partial Approval RAUL OLAGI
HVAC-Rough 12/19/2025 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 1/29/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 2/6/2026 Corrections Issued KIRK SANDERS
Special/Order Compliance 2/6/2026 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 2/25/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 2/25/2026 Approved CHRISTOPHER ROJAS
Green Building Rough 2/25/2026 Approved CHRISTOPHER ROJAS
Grounding or Bonding 2/25/2026 Approved CHRISTOPHER ROJAS
HVAC-Rough 2/25/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 3/2/2026 Approved KEVIN BERBERYAN