2119 S SELBY AVE 90025

Certificate Information: 2119 S SELBY AVE 90025

Application / Permit
24014-10000-04148
Plan Check / Job No.
B24LA22703
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Addition to single family dwelling and breezeway.
Permit Issued
Issued on 11/1/2024
Issuing Office
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2024 APPLICANT
Assigned to Plan Check Engineer 9/18/2024 KELVIN CHUONG
Corrections Issued 9/19/2024 KELVIN CHUONG
Applicant returned to address corrections 9/27/2024 RICARDO RAMIREZ
Applicant returned to address corrections 10/1/2024 KELVIN CHUONG
Plan Check Approved 10/13/2024 SAMUEL GONZALEZ
Issued 11/1/2024 APPLICANT
CofO in Progress 4/22/2025 KIRK SANDERS
Permit Finaled 4/24/2025 RICHARD STEINBACH
Permit Finaled 4/24/2025 RICHARD STEINBACH
CofO Issued 4/24/2025 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 9/28/2024 DARIN LAM
Specific Plan Cleared 9/30/2024 RICHARD WOO
Grading Pre-Inspection Cleared 10/4/2024 VASIL MIHALEV
Eng Process Fee Ord 176,300 Cleared 10/7/2024 DARIN LAM
Roof/Waste drainage to street Cleared 10/10/2024 DARIN LAM

Contact Information

Contractor Vam Construction Corp; Lic. No.: 1078047-B       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/27/2024 Approved ARAM AVEDISIAN
PLUMBING-Rough 12/10/2024 Partial Approval KIRK SANDERS
Wood Frame 12/10/2024 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 12/12/2024 Conditional Approval KIRK SANDERS
Insulation 12/12/2024 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 1/15/2025 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 1/15/2025 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/15/2025 Approved KIRK SANDERS
Green Building Rough 1/15/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 1/15/2025 Approved KIRK SANDERS
PLUMBING-Rough 1/15/2025 Corrections Issued KIRK SANDERS
Insulation 1/29/2025 Conditional Approval KIRK SANDERS
Interior/Exterior Lathing 1/29/2025 Approved KIRK SANDERS
Shower Pan 1/29/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 2/4/2025 Approved KIRK SANDERS
Drywall Nailing 2/4/2025 Approved KIRK SANDERS
Green Building Rough 2/4/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 2/4/2025 Approved KIRK SANDERS
PLUMBING-Rough 2/4/2025 Approved KIRK SANDERS
ELECTRICAL-Final 4/18/2025 Not Ready for Inspection SEAN HAUPT
Final 4/18/2025 Corrections Issued SEAN HAUPT
Green Building Final 4/18/2025 Not Ready for Inspection SEAN HAUPT
HVAC-Final 4/18/2025 Not Ready for Inspection SEAN HAUPT
PLUMBING-Final 4/18/2025 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 4/18/2025 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 4/18/2025 Not Ready for Inspection SEAN HAUPT
Final 4/22/2025 OK to Issue CofO KIRK SANDERS
Green Building Final 4/22/2025 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 4/22/2025 SGSOV Approved KIRK SANDERS
Smoke Detectors 4/22/2025 Approved KIRK SANDERS