8316 S WINSFORD AVE 90045

Certificate Information: 8316 S WINSFORD AVE 90045

Application / Permit
24014-10000-04146
Plan Check / Job No.
B24LA22699
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*Eplan.* (N) 2-story ADU addition to (E) garage per LAMC 12.22 A.33 (c)-(d). Resulting in detached ADU w/ attached garage.
Permit Issued
Issued on 1/9/2025
Issuing Office
Current Status
CofO Issued on 7/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 HUAN LE
Corrections Issued 11/6/2024 HUAN LE
Quality Review Completed 11/7/2024 JOHN FRANCIA
Applicant returned to address corrections 12/27/2024 HUAN LE
Plan Check Approved 1/9/2025 HUAN LE
Issued 1/9/2025 APPLICANT
CofO in Progress 7/21/2025 BOBBY KEY
Permit Finaled 7/22/2025 RICHARD STEINBACH
CofO Issued 7/22/2025 RICHARD STEINBACH
Permit Finaled 7/22/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 12/4/2024 VLADIMIR ARUTYUNYAN
Eng Process Fee Ord 176,300 Cleared 12/6/2024 DIANA RENTERIA
Roof/Waste drainage to street Cleared 12/6/2024 DIANA RENTERIA
Sewer availability Cleared 12/6/2024 DIANA RENTERIA
Specific Plan Cleared 12/10/2024 JOSHUA JONES
Grading Pre-Inspection Cleared 12/27/2024 HUAN LE
GPI Written Notices Cleared 1/9/2025 JOHN FRANCIA

Contact Information

Architect Pil, Sun Olivia Ham; Lic. No.: C36231       ,
Contractor Home Creations Inc; Lic. No.: 1057627-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/10/2025 Conditional Approval TEMISTOCLES CAAL
PLUMBING-Rough 1/13/2025 Partial Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 1/15/2025 Corrections Issued TEMISTOCLES CAAL
Footing/Foundation/Slab 1/28/2025 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Corrections Issued BOBBY KEY
Deputy Wood Construction 2/28/2025 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 3/18/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 3/18/2025 Approved JESUS PINEDA
Green Building Rough 3/18/2025 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 3/18/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 3/18/2025 Corrections Issued JESUS PINEDA
PLUMBING-Rough 3/18/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 3/24/2025 Partial Approval RUBEN RIVAS
ELECTRICAL-Rough 3/24/2025 Corrections Issued RUBEN RIVAS
Green Building Rough 3/24/2025 Partial Approval RUBEN RIVAS
Interior/Exterior Lathing 3/24/2025 Approved RUBEN RIVAS
Shower Pan 3/24/2025 Approved RUBEN RIVAS
Special/Order Compliance 3/24/2025 Partial Inspection BOBBY KEY
Wood Frame 3/24/2025 Partial Approval RUBEN RIVAS
ELECTRICAL-Rough 3/28/2025 Partial Approval RUBEN RIVAS
Insulation 3/28/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 4/4/2025 Approved JESUS PINEDA
Drywall Nailing 4/4/2025 Corrections Issued JESUS PINEDA
Green Building Rough 4/4/2025 Approved JESUS PINEDA
Drywall Nailing 4/22/2025 Approved JAYLIN GRAVITTE
Final 5/28/2025 Corrections Issued JESUS PINEDA
Green Building Final 5/28/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 5/28/2025 SGSOV Not Required JESUS PINEDA
Smoke Detectors 5/28/2025 Approved JESUS PINEDA
Final 6/3/2025 Corrections Issued TEMISTOCLES CAAL
Final 6/20/2025 Corrections Issued BOBBY KEY
Final 7/21/2025 OK to Issue CofO BOBBY KEY
Service/Power Release 7/21/2025 Approved BOBBY KEY