2937-2939 S 10TH AVE 90018

Certificate Information: 2937-2939 S 10TH AVE 90018

Application / Permit
24014-10000-04140
Plan Check / Job No.
B24LA22636
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) ADDITION TO THE (E) TWO FAMILY DWELLING UNITS.
Permit Issued
Issued on 3/6/2025
Issuing Office
Metro
Current Status
CofO Issued on 4/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2024 APPLICANT
Assigned to Plan Check Engineer 9/19/2024 VARAND SARKISIAN
Corrections Issued 9/24/2024 VARAND SARKISIAN
Quality Review Completed 9/27/2024 KEN GILL
Building Plans Picked Up 10/1/2024 APPLICANT
Plan Check Approved 11/15/2024 VARAND SARKISIAN
Issued 3/6/2025 APPLICANT
CofO in Progress 4/2/2026 JUSTIN HAWLEY
Permit Finaled 4/5/2026 DEROLD HAUFF
CofO Issued 4/5/2026 DEROLD HAUFF
Permit Finaled 4/5/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/16/2024 ADRIAN SANCHEZ
Tenant Habitability Plan Cleared 11/1/2024 RICARDO BOHORQUEZ
Eng Process Fee Ord 176,300 Cleared 11/5/2024 JEANIE LAM
Sewer availability Cleared 11/5/2024 JEANIE LAM

Contact Information

Contractor Sa Home Restoration; Lic. No.: 1102417-B 76 MEADOWOOD      ALISO VIEJO, CA 92656
Engineer Moeini,, Soheil; Lic. No.: C84000 11022 SANTA MONICA BLVD STE 440      LOS ANGELES, CA 90025

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/18/2025 Approved JUSTIN HAWLEY
Underground Mechanical 7/18/2025 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 8/4/2025 Not Ready for Inspection ARTHUR NEGRETE
Green Building Rough 8/4/2025 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 8/7/2025 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 8/29/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 9/19/2025 Not Ready for Inspection JUSTIN HAWLEY
Gas Test 9/19/2025 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 9/19/2025 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 9/29/2025 Approved JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 9/29/2025 Approved JUSTIN HAWLEY
Insulation 10/3/2025 Approved JUSTIN HAWLEY
Drywall Nailing 10/21/2025 Approved DEVON JACKSON
Interior/Exterior Lathing 10/21/2025 Partial Approval DEVON JACKSON
Shower Pan 10/21/2025 Approved DEVON JACKSON
Interior/Exterior Lathing 10/28/2025 Approved JUSTIN HAWLEY
Service/Power Release 12/3/2025 Not Ready for Inspection JUSTIN HAWLEY
ELECTRICAL-Final 12/29/2025 Approved JUSTIN HAWLEY
Smoke Detectors 12/29/2025 Approved JUSTIN HAWLEY
Final 2/2/2026 Corrections Issued JUSTIN HAWLEY
Final 3/27/2026 Corrections Issued JUSTIN HAWLEY
Final 4/2/2026 OK to Issue CofO JUSTIN HAWLEY
Green Building Final 4/2/2026 Approved JUSTIN HAWLEY
HVAC-Final 4/2/2026 Approved JUSTIN HAWLEY
PLUMBING-Final 4/2/2026 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 4/2/2026 SGSOV Approved JUSTIN HAWLEY
Service/Power Release 4/2/2026 Approved JUSTIN HAWLEY