8909-8911 N WAKEFIELD AVE 91402

Certificate Information: 8909-8911 N WAKEFIELD AVE 91402

Application / Permit
24014-10000-04117
Plan Check / Job No.
B24VN14071
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
eplan 2nd story addition to create 2nd SFD per SB9 Two unit development CA GOVT 65852.21. New SB9 to be fully sprinklered. And new addition to (e) SFD.
Permit Issued
Issued on 7/9/2025
Issuing Office
Current Status
CofO Issued on 6/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2024 APPLICANT
Assigned to Plan Check Engineer 9/5/2024 MARCELA FRANQUEZ
Corrections Issued 9/12/2024 MARCELA FRANQUEZ
Quality Review Completed 9/19/2024 TU HUA
Applicant returned to address corrections 5/20/2025 MARCELA FRANQUEZ
Applicant returned to address corrections 6/11/2025 MARCELA FRANQUEZ
Applicant returned to address corrections 6/27/2025 MARCELA FRANQUEZ
Plan Check Approved 7/2/2025 MARCELA FRANQUEZ
Issued 7/9/2025 APPLICANT
CofO in Progress 5/22/2026 OGANES TARAKHCHYAN
Permit Finaled 6/12/2026 RUBEN SALAS
CofO Issued 6/12/2026 RUBEN SALAS
Permit Finaled 6/12/2026 RUBEN SALAS

Permit Application Clearance Information

Senate Bill 9 Cleared 5/1/2025 JACQUELINE TORRES
Address approval Cleared 5/2/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 5/2/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/7/2025 RYAN CASTRO
Sewer availability Cleared 5/7/2025 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Vartanian,, Albert; Lic. No.: C39989 1250 W GLENOAKS BLVD E355      GLENDALE, CA 91201

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/12/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 9/12/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/23/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/23/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Partial Approval VINCENT HANLEY
PLUMBING-Rough 10/3/2025 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 10/9/2025 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/9/2025 Partial Approval VINCENT HANLEY
Green Building Rough 10/9/2025 Not Ready for Inspection VINCENT HANLEY
Wood Frame 10/29/2025 Corrections Issued VINCENT HANLEY
Rough-Elec/Plmb/HVAC 11/4/2025 Corrections Issued JACK KARGODORIAN
Interior/Exterior Lathing 11/7/2025 Partial Approval WILLIAM WREN
ELECTRICAL-Rough 11/12/2025 Approved JOSE AVILA
Wood Frame 11/26/2025 Approved OGANES TARAKHCHYAN
Insulation 12/10/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Insulation 12/12/2025 Approved LOUIS ESCOTO
Shower Pan 12/12/2025 Approved LOUIS ESCOTO
Drywall Nailing 12/24/2025 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 12/24/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/23/2026 Approved MATTHEW NELSON
Underground Mechanical 2/3/2026 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 4/29/2026 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/11/2026 Approved OGANES TARAKHCHYAN
Drywall Nailing 5/11/2026 Approved OGANES TARAKHCHYAN
Final 5/11/2026 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 5/11/2026 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/11/2026 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 5/11/2026 Approved OGANES TARAKHCHYAN
Smoke Detectors 5/11/2026 Approved OGANES TARAKHCHYAN
Final 5/22/2026 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 5/22/2026 Approved OGANES TARAKHCHYAN