8909-8911 N WAKEFIELD AVE 91402
Certificate Information: 8909-8911 N WAKEFIELD AVE 91402
- Application / Permit
- 24014-10000-04117
- Plan Check / Job No.
- B24VN14071
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- eplan 2nd story addition to create 2nd SFD per SB9 Two unit development CA GOVT 65852.21. New SB9 to be fully sprinklered. And new addition to (e) SFD.
- Permit Issued
- Issued on 7/9/2025
- Issuing Office
- Current Status
- CofO Issued on 6/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 9/12/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 9/19/2024 | TU HUA |
| Applicant returned to address corrections | 5/20/2025 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 6/11/2025 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 6/27/2025 | MARCELA FRANQUEZ |
| Plan Check Approved | 7/2/2025 | MARCELA FRANQUEZ |
| Issued | 7/9/2025 | APPLICANT |
| CofO in Progress | 5/22/2026 | OGANES TARAKHCHYAN |
| Permit Finaled | 6/12/2026 | RUBEN SALAS |
| CofO Issued | 6/12/2026 | RUBEN SALAS |
| Permit Finaled | 6/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Senate Bill 9 | Cleared | 5/1/2025 | JACQUELINE TORRES |
| Address approval | Cleared | 5/2/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 5/2/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 5/7/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | 1250 W GLENOAKS BLVD E355 GLENDALE, CA 91201 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/12/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 9/12/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 9/23/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2025 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2025 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 10/3/2025 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/9/2025 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 10/9/2025 | Not Ready for Inspection | VINCENT HANLEY |
| Wood Frame | 10/29/2025 | Corrections Issued | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 11/4/2025 | Corrections Issued | JACK KARGODORIAN |
| Interior/Exterior Lathing | 11/7/2025 | Partial Approval | WILLIAM WREN |
| ELECTRICAL-Rough | 11/12/2025 | Approved | JOSE AVILA |
| Wood Frame | 11/26/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 12/10/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Insulation | 12/12/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 12/12/2025 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 12/24/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 12/24/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/23/2026 | Approved | MATTHEW NELSON |
| Underground Mechanical | 2/3/2026 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 4/29/2026 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/11/2026 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/11/2026 | Approved | OGANES TARAKHCHYAN |
| Final | 5/11/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 5/11/2026 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 5/11/2026 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 5/11/2026 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 5/11/2026 | Approved | OGANES TARAKHCHYAN |
| Final | 5/22/2026 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 5/22/2026 | Approved | OGANES TARAKHCHYAN |