7901 S WINSFORD AVE 90045

Certificate Information: 7901 S WINSFORD AVE 90045

Application / Permit
24014-10000-04096
Plan Check / Job No.
B24LA22380
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One story addition and interior remodel to (E) one-story Single Family Dwelling. Work per Engineered design. Building to be Sprinklered.
Permit Issued
Issued on 10/30/2024
Issuing Office
Current Status
CofO Issued on 7/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2024 APPLICANT
Assigned to Plan Check Engineer 9/16/2024 EDWIN MARTINEZ
Corrections Issued 9/17/2024 EDWIN MARTINEZ
Building Plans Picked Up 9/26/2024 APPLICANT
Applicant returned to address corrections 10/11/2024 ARSALAN SHABESTARI
Plan Check Approved 10/24/2024 CARLOS MONTES
Issued 10/30/2024 APPLICANT
CofO in Progress 7/25/2025 BOBBY KEY
Permit Finaled 7/29/2025 RICHARD STEINBACH
CofO Issued 7/29/2025 RICHARD STEINBACH
Permit Finaled 7/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 9/17/2024 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 9/19/2024 HISASHI KOBAYAKAWA
Sewer availability Cleared 9/19/2024 HISASHI KOBAYAKAWA
Grading Pre-Inspection Cleared 9/23/2024 VASIL MIHALEV
Roof/Waste drainage to street Cleared 9/25/2024 VLADIMIR ARUTYUNYAN
GPI Written Notices Cleared 10/9/2024 EDWIN MARTINEZ
Disturb/Remove Protected Trees Cleared 10/21/2024 RICHARD SANCHEZ

Contact Information

Architect Asamoah,, B Kwesi; Lic. No.: C36558 850 ROSE AVENUE      VENICE, CA 90291
Contractor H T A Construction & Development; Lic. No.: 1044038-B 3639 ATLANTIC AVE      LONG BEACH, CA 90807
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/9/2024 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Rough 12/9/2024 Corrections Issued TEMISTOCLES CAAL
Pre-Inspection 12/9/2024 Partial Inspection TEMISTOCLES CAAL
Footing/Foundation/Slab 12/17/2024 Approved TEMISTOCLES CAAL
PLUMBING-Rough 12/17/2024 Partial Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 3/7/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Corrections Issued TEMISTOCLES CAAL
HVAC-Rough 3/7/2025 Approved TEMISTOCLES CAAL
PLUMBING-Rough 3/7/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 3/13/2025 Approved HERBERT GIRON
Special/Order Compliance 3/13/2025 Conditional Approval JESUS PINEDA
Special/Order Compliance 3/13/2025 Partial Inspection TEMISTOCLES CAAL
Wood Frame 3/13/2025 Not Ready for Inspection HERBERT GIRON
Wood Frame 3/24/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 4/7/2025 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 4/7/2025 Approved TEMISTOCLES CAAL
Green Building Rough 4/7/2025 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 4/7/2025 Corrections Issued TEMISTOCLES CAAL
Verify Sprinkler Sign Off 4/7/2025 Approved TEMISTOCLES CAAL
Insulation 4/15/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 4/15/2025 Approved JAYLIN GRAVITTE
Drywall Nailing 4/21/2025 Approved JAYLIN GRAVITTE
Shower Pan 4/21/2025 Partial Approval JAYLIN GRAVITTE
Interior/Exterior Lathing 5/5/2025 Approved JESUS PINEDA
Shower Pan 5/5/2025 Approved JESUS PINEDA
Special/Order Compliance 5/5/2025 Corrections Issued JESUS PINEDA
Special/Order Compliance 5/5/2025 Partial Inspection JAYLIN GRAVITTE
ELECTRICAL-Final 6/6/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Final 6/10/2025 Not Ready for Inspection JESUS PINEDA
Final 6/13/2025 Corrections Issued JESUS PINEDA
Gas Test 6/13/2025 Corrections Issued JESUS PINEDA
Green Building Final 6/13/2025 Corrections Issued JESUS PINEDA
HVAC-Final 6/13/2025 Corrections Issued JESUS PINEDA
PLUMBING-Final 6/13/2025 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 6/13/2025 SGSOV Not Ready JESUS PINEDA
Smoke Detectors 6/13/2025 Approved JESUS PINEDA
ELECTRICAL-Final 6/18/2025 Corrections Issued RUBEN RIVAS
ELECTRICAL-Final 6/23/2025 Approved ARAM AVEDISIAN
Service/Power Release 6/23/2025 Approved ARAM AVEDISIAN
PLUMBING-Final 6/25/2025 Approved BOBBY KEY
Final 6/26/2025 Corrections Issued RUBEN RIVAS
Green Building Final 6/26/2025 Partial Approval RUBEN RIVAS
HVAC-Final 6/26/2025 Partial Approval RUBEN RIVAS
PLUMBING-Final 6/26/2025 Approved RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 6/26/2025 SGSOV Approved RUBEN RIVAS
HVAC-Final 6/27/2025 Partial Approval RUBEN RIVAS
PLUMBING-Final 6/27/2025 Approved RUBEN RIVAS
Pre-Inspection 7/21/2025 Partial Inspection BOBBY KEY
Final 7/25/2025 OK to Issue CofO BOBBY KEY
Green Building Final 7/25/2025 Approved BOBBY KEY
HVAC-Final 7/25/2025 Approved BOBBY KEY