8513 S RAMSGATE AVE 90045

Certificate Information: 8513 S RAMSGATE AVE 90045

Application / Permit
24014-10000-04057
Plan Check / Job No.
B24LA21932
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
IRREGULAR SHAPED ADDITION TO THE EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
Permit Issued
Issued on 10/25/2024
Issuing Office
Current Status
CofO Issued on 5/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2024 APPLICANT
Assigned to Plan Check Engineer 9/13/2024 DANIEL ABRAMYAN
Corrections Issued 9/16/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 9/20/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 9/24/2024 SERGIO MUNIZ
Applicant returned to address corrections 9/25/2024 SERGIO MUNIZ
Plan Check Approved 10/24/2024 SERGIO MUNIZ
Issued 10/25/2024 APPLICANT
CofO in Progress 5/6/2025 RUBEN RIVAS
Permit Finaled 5/20/2025 RICHARD STEINBACH
CofO Issued 5/20/2025 RICHARD STEINBACH
Permit Finaled 5/20/2025 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/16/2024 DANIEL ABRAMYAN
Sewer availability Cleared 9/17/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 9/18/2024 DARIN LAM
Roof/Waste drainage to street Cleared 9/24/2024 DARIN LAM
Specific Plan Cleared 10/22/2024 FREDDY GARCIA

Contact Information

Contractor Carter Design & Remodeling Inc; Lic. No.: 932102-B       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/29/2024 Partial Inspection BOBBY KEY
Deputy Drilled-In Anchors 11/13/2024 Conditional Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 11/14/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/2/2024 Partial Approval TEMISTOCLES CAAL
PLUMBING-Rough 12/2/2024 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/27/2024 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 12/31/2024 Approved TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 1/16/2025 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 1/28/2025 Approved BOBBY KEY
Green Building Rough 1/28/2025 Approved BOBBY KEY
Interior/Exterior Lathing 1/28/2025 Partial Approval BOBBY KEY
Rough-Elec/Plmb/HVAC 1/28/2025 Approved BOBBY KEY
Insulation 1/30/2025 Approved BOBBY KEY
Drywall Nailing 2/6/2025 Approved BOBBY KEY
Special/Order Compliance 2/6/2025 Partial Inspection TEMISTOCLES CAAL
Shower Pan 2/21/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 2/24/2025 Approved TEMISTOCLES CAAL
Gas Test 3/4/2025 Approved TEMISTOCLES CAAL
Green Building Final 4/18/2025 No Access for Inspection TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 4/18/2025 SGSOV Not Required TEMISTOCLES CAAL
Smoke Detectors 4/18/2025 No Access for Inspection TEMISTOCLES CAAL
Special/Order Compliance 4/18/2025 No Access for Inspection JAYLIN GRAVITTE
Special/Order Compliance 4/18/2025 Partial Inspection HERBERT GIRON
ELECTRICAL-Final 5/2/2025 Approved RUBEN RIVAS
Final 5/2/2025 OK to Issue CofO RUBEN RIVAS
Green Building Final 5/2/2025 Approved RUBEN RIVAS
HVAC-Final 5/2/2025 Approved RUBEN RIVAS
PLUMBING-Final 5/2/2025 Approved RUBEN RIVAS
Smoke Detectors 5/2/2025 Approved RUBEN RIVAS