8513 S RAMSGATE AVE 90045
Certificate Information: 8513 S RAMSGATE AVE 90045
- Application / Permit
- 24014-10000-04057
- Plan Check / Job No.
- B24LA21932
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRREGULAR SHAPED ADDITION TO THE EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 10/25/2024
- Issuing Office
- Current Status
- CofO Issued on 5/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/13/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 9/16/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 9/20/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 9/24/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 9/25/2024 | SERGIO MUNIZ |
| Plan Check Approved | 10/24/2024 | SERGIO MUNIZ |
| Issued | 10/25/2024 | APPLICANT |
| CofO in Progress | 5/6/2025 | RUBEN RIVAS |
| Permit Finaled | 5/20/2025 | RICHARD STEINBACH |
| CofO Issued | 5/20/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/20/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/16/2024 | DANIEL ABRAMYAN |
| Sewer availability | Cleared | 9/17/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2024 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 9/24/2024 | DARIN LAM |
| Specific Plan | Cleared | 10/22/2024 | FREDDY GARCIA |
Contact Information
| Contractor | Carter Design & Remodeling Inc; Lic. No.: 932102-B | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/29/2024 | Partial Inspection | BOBBY KEY |
| Deputy Drilled-In Anchors | 11/13/2024 | Conditional Approval | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 11/14/2024 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 12/2/2024 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2024 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 12/31/2024 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2025 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 1/28/2025 | Approved | BOBBY KEY |
| Green Building Rough | 1/28/2025 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/28/2025 | Partial Approval | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 1/28/2025 | Approved | BOBBY KEY |
| Insulation | 1/30/2025 | Approved | BOBBY KEY |
| Drywall Nailing | 2/6/2025 | Approved | BOBBY KEY |
| Special/Order Compliance | 2/6/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Shower Pan | 2/21/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 2/24/2025 | Approved | TEMISTOCLES CAAL |
| Gas Test | 3/4/2025 | Approved | TEMISTOCLES CAAL |
| Green Building Final | 4/18/2025 | No Access for Inspection | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 4/18/2025 | SGSOV Not Required | TEMISTOCLES CAAL |
| Smoke Detectors | 4/18/2025 | No Access for Inspection | TEMISTOCLES CAAL |
| Special/Order Compliance | 4/18/2025 | No Access for Inspection | JAYLIN GRAVITTE |
| Special/Order Compliance | 4/18/2025 | Partial Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 5/2/2025 | Approved | RUBEN RIVAS |
| Final | 5/2/2025 | OK to Issue CofO | RUBEN RIVAS |
| Green Building Final | 5/2/2025 | Approved | RUBEN RIVAS |
| HVAC-Final | 5/2/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 5/2/2025 | Approved | RUBEN RIVAS |
| Smoke Detectors | 5/2/2025 | Approved | RUBEN RIVAS |