3104 S DANNYHILL DR 90064

Certificate Information: 3104 S DANNYHILL DR 90064

Application / Permit
24014-10000-04037
Plan Check / Job No.
B24LA21747
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 13'9" X 16'6" ADDITION TO REAR OF EXISTING SINGLE FAMILY DWELLING TO ADD A NEW DEN / GYM SPACE TO THE MASTER SUITE. WORK DONE PER ARCHITECT DESIGN.
Permit Issued
Issued on 3/12/2025
Issuing Office
Current Status
CofO Issued on 9/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2024 APPLICANT
Assigned to Plan Check Engineer 9/18/2024 SERGIO MUNIZ
Corrections Issued 9/19/2024 SERGIO MUNIZ
Applicant returned to address corrections 10/21/2024 SERGIO MUNIZ
Plan Check Approved 10/30/2024 MADISON O'DELL
Issued 3/12/2025 APPLICANT
Permit Finaled 9/29/2025 RICHARD STEINBACH
CofO Issued 9/29/2025 RICHARD STEINBACH
Permit Finaled 9/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/7/2024 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 10/8/2024 LIAM ODONOVAN
Specific Plan Cleared 10/16/2024 FREDDY GARCIA
Grading Pre-Inspection Cleared 10/24/2024 MATTHEW JENKINS

Contact Information

Architect Krunic,, Dina; Lic. No.: NA38613       ,
Contractor Bovee Construction Inc; Lic. No.: 702219-B       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/28/2025 Partial Approval ASHLEY THOMPSON
Footing/Foundation/Slab 5/28/2025 Approved ASHLEY THOMPSON
ELECTRICAL-Rough 6/30/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/30/2025 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 7/7/2025 Approved ARAM AVEDISIAN
HVAC-Rough 7/7/2025 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 7/18/2025 Approved ARAM AVEDISIAN
Green Building Rough 7/18/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 7/18/2025 Partial Approval ARAM AVEDISIAN
Insulation 8/4/2025 Corrections Issued ASHLEY THOMPSON
Drywall Nailing 8/7/2025 Conditional Approval MEL KHACHATOURIAN
ELECTRICAL-Final 9/16/2025 Approved MICHAEL ALLEN
Final 9/16/2025 Corrections Issued MICHAEL ALLEN
Green Building Final 9/16/2025 Conditional Approval MICHAEL ALLEN
HVAC-Final 9/16/2025 Conditional Approval MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 9/16/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 9/16/2025 Approved MICHAEL ALLEN
Final 9/29/2025 Conditional Approval MICHAEL PELHAM
Green Building Final 9/29/2025 Approved MICHAEL PELHAM