3362 S ROSEWOOD AVE 90066

Certificate Information: 3362 S ROSEWOOD AVE 90066

Application / Permit
24014-10000-04011
Plan Check / Job No.
B24LA21529
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. SUPPLEMENTAL TO 23014-10000-04052. FOR NEW 2ND STORY ADDITION
Permit Issued
Issued on 3/14/2025
Issuing Office
Current Status
CofO Issued on 12/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2024 APPLICANT
Assigned to Plan Check Engineer 9/12/2024 KEVIN MORALES
Corrections Issued 9/17/2024 KEVIN MORALES
Quality Review Completed 9/18/2024 EUGENE BARBEAU
Applicant returned to address corrections 2/5/2025 KEVIN MORALES
Applicant returned to address corrections 3/4/2025 KEVIN MORALES
Plan Check Approved 3/12/2025 KEVIN MORALES
Plan Check Approved 3/14/2025 KEVIN MORALES
Issued 3/14/2025 APPLICANT
CofO in Progress 12/11/2025 RYAN BARNES
Permit Finaled 12/15/2025 CLAUDIO MORENO
CofO Issued 12/15/2025 CLAUDIO MORENO
Permit Finaled 12/15/2025 CLAUDIO MORENO

Permit Application Clearance Information

Low Impact Development (LID) Cleared 1/2/2025 ERNEST TSE
Eng Process Fee Ord 176,300 Cleared 1/8/2025 LIAM ODONOVAN
Sewer availability Cleared 1/8/2025 LIAM ODONOVAN
Grading Pre-Inspection Cleared 1/12/2025 VASIL MIHALEV
Roof/Waste drainage to street Cleared 1/14/2025 DARIN LAM
Specific Plan Cleared 2/10/2025 RICHARD WOO
GPI Written Notices Cleared 3/12/2025 KEVIN MORALES

Contact Information

Contractor Owner-Builder       ,
Engineer Paniagua,, Cristobal; Lic. No.: NA72894       ,

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/17/2025 Approved RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Partial Approval RYAN BARNES
Wood Frame 4/10/2025 Partial Approval RYAN BARNES
BUILDING-Rough-Frame 4/21/2025 Partial Approval JOHN MATTILLO
ELECTRICAL-Rough 5/19/2025 Corrections Issued RYAN BARNES
HVAC-Rough 5/19/2025 Corrections Issued RYAN BARNES
PLUMBING-Rough 5/19/2025 Approved RYAN BARNES
ELECTRICAL-Final 10/10/2025 Approved RYAN BARNES
Service/Power Release 10/10/2025 Approved RYAN BARNES
BUILDING-Rough-Frame 12/11/2025 Approved RYAN BARNES
Final 12/11/2025 OK to Issue CofO RYAN BARNES
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV Approved RYAN BARNES
Smoke Detectors 12/11/2025 Approved RYAN BARNES