4620-4620 1/2 E TWINING ST 90032
Certificate Information: 4620-4620 1/2 E TWINING ST 90032
- Application / Permit
- 24014-10000-03999
- Plan Check / Job No.
- B24LA21474
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERSION OF LOWER LEVEL OF (E) 1-STORY SFD TO ADU PER LAMC 12.22 A.33(c) and (e) WITH INT. AND EXT. STRUCTURAL REMODEL AND (N) ATTACHED DECK
- Permit Issued
- Issued on 3/13/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 9/27/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 10/4/2024 | KEN GILL |
| Building Plans Picked Up | 10/24/2024 | APPLICANT |
| Applicant returned to address corrections | 2/28/2025 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 3/6/2025 | MAHNAZ NOURHASHEMI |
| Issued | 3/13/2025 | APPLICANT |
| CofO in Progress | 4/16/2026 | LILIANA PORTILLO |
| Permit Finaled | 4/17/2026 | DEROLD HAUFF |
| CofO Issued | 4/17/2026 | DEROLD HAUFF |
| Permit Finaled | 4/17/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| "D" conditions | Cleared | 10/29/2024 | DALIA MOKAYED |
| "Q" conditions | Cleared | 10/29/2024 | DALIA MOKAYED |
| ZI | Cleared | 10/29/2024 | DALIA MOKAYED |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2024 | STEVE MELGAR |
| Sewer availability | Cleared | 12/9/2024 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 1/17/2025 | LAVEON RIDER |
| Address approval | Cleared | 2/28/2025 | AMBER CAMPBELL |
| GPI Written Notices | Cleared | 2/28/2025 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 2/28/2025 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Carraher Norman Joseph Jr; Lic. No.: 813208-B | 17405 FFAIRFAX FONTANA, CA 92336 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/18/2025 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/25/2025 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/19/2025 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/22/2025 | Corrections Issued | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 5/28/2025 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/28/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 6/9/2025 | Partial Approval | LILIANA PORTILLO |
| HVAC-Rough | 6/17/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/15/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 7/15/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 7/15/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 7/15/2025 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 7/28/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 9/8/2025 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 9/8/2025 | Conditional Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 9/8/2025 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/17/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/17/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 9/17/2025 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2025 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 10/2/2025 | Approved | GEM DE OCAMPO |
| Drywall Nailing | 10/10/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 10/10/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 10/21/2025 | Approved | GEM DE OCAMPO |
| Shower Pan | 10/23/2025 | Approved | GEM DE OCAMPO |
| Gas Test | 12/12/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/13/2026 | Approved | LILIANA PORTILLO |
| Final | 2/13/2026 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 2/13/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Rough | 2/13/2026 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 2/13/2026 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 2/13/2026 | Approved | LILIANA PORTILLO |
| Final | 4/6/2026 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 4/6/2026 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/6/2026 | SGSOV Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 4/15/2026 | Approved | LILIANA PORTILLO |
| Final | 4/15/2026 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 4/15/2026 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 4/15/2026 | Approved | LILIANA PORTILLO |
| Service/Power Release | 4/15/2026 | Approved | LILIANA PORTILLO |