10332-10332 1/2 S JUNIPER ST 90002

Certificate Information: 10332-10332 1/2 S JUNIPER ST 90002

Application / Permit
24014-10000-03998
Plan Check / Job No.
B24LA21472
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. Addition to rear side of (e) SFD w./ att. ADU to add a bedroom, bathroom and laundry room to ADU
Permit Issued
Issued on 10/4/2024
Issuing Office
Current Status
CofO Issued on 7/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2024 APPLICANT
Assigned to Plan Check Engineer 9/10/2024 REZA HAGHIGHAT
Corrections Issued 9/10/2024 REZA HAGHIGHAT
Applicant returned to address corrections 9/26/2024 DAVID CASTILLO
Plan Check Approved 10/4/2024 DAVID CASTILLO
Issued 10/4/2024 APPLICANT
CofO in Progress 7/14/2025 JOSEPH MCGARRY
Permit Finaled 7/14/2025 ANSON MAGLASANG
CofO Issued 7/14/2025 ANSON MAGLASANG
Permit Finaled 7/14/2025 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/16/2024 JESSICA OPINION
Sewer availability Cleared 9/16/2024 JESSICA OPINION

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng D; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/2/2025 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 1/8/2025 Partial Approval ANTHONY EGSON
PLUMBING-Rough 1/8/2025 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 1/10/2025 No Access for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 1/14/2025 Approved ANTHONY EGSON
Footing/Foundation/Slab 1/14/2025 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 1/16/2025 Approved ANTHONY EGSON
Footing/Foundation/Slab 1/16/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 2/27/2025 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 2/27/2025 Not Ready for Inspection JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 2/27/2025 Approved JOSEPH MCGARRY
HVAC-Rough 2/27/2025 Corrections Issued JOSEPH MCGARRY
PLUMBING-Rough 2/27/2025 Approved JOSEPH MCGARRY
Deputy Wood Construction 3/3/2025 Conditional Approval ANSON MAGLASANG
ELECTRICAL-Rough 3/3/2025 Not Ready for Inspection ANTHONY EGSON
Interior/Exterior Lathing 3/3/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 3/7/2025 Approved ANTHONY EGSON
ELECTRICAL-Rough 3/7/2025 Approved ANTHONY EGSON
Green Building Rough 3/7/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 4/14/2025 Approved JOSEPH MCGARRY
HVAC-Rough 4/14/2025 Approved JOSEPH MCGARRY
Insulation 4/14/2025 Approved JOSEPH MCGARRY
Drywall Nailing 4/24/2025 Not Ready for Inspection ANTHONY EGSON
Interior/Exterior Lathing 4/24/2025 Corrections Issued EUGENE CASSIDY
Drywall Nailing 4/28/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 4/28/2025 Approved ANTHONY EGSON
Final 7/3/2025 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 7/3/2025 Approved ANTHONY EGSON
PLUMBING-Final 7/3/2025 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 7/3/2025 SGSOV Not Required ANTHONY EGSON
Smoke Detectors 7/3/2025 Not Ready for Inspection ANTHONY EGSON
Final 7/8/2025 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 7/8/2025 Corrections Issued ANTHONY EGSON
Final 7/10/2025 OK to Issue CofO JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/10/2025 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 7/10/2025 Approved JOSEPH MCGARRY