403 E KENDALL AVE 90042
Certificate Information: 403 E KENDALL AVE 90042
- Application / Permit
- 24014-10000-03986
- Plan Check / Job No.
- B24LA21388
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN: INTERIOR REMODEL OF (E) DUPLEX AND 26'3" x 14' IRREG. SHAPED ADDITION TO THE REAR OF UNIT # 403) . WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 10/14/2024
- Issuing Office
- Current Status
- Issued on 10/14/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 9/10/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 9/24/2024 | ARAMIK SHAHMIRZAIAN |
| Applicant returned to address corrections | 9/26/2024 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 10/3/2024 | KAMYAR EMAMI |
| Issued | 10/14/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/17/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 9/17/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2024 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/29/2024 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/13/2024 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 11/13/2024 | Approved | LILIANA PORTILLO |
| Insulation | 11/13/2024 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2024 | Partial Approval | LILIANA PORTILLO |
| Deputy Wood Construction | 12/4/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 12/4/2024 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Corrections Issued | LILIANA PORTILLO |
| Green Building Rough | 12/4/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 12/10/2024 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 12/10/2024 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 12/23/2024 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 12/23/2024 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 12/23/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 12/23/2024 | Partial Approval | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 12/26/2024 | Conditional Approval | LILIANA PORTILLO |
| Green Building Rough | 12/26/2024 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 12/26/2024 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 1/21/2025 | Approved | LILIANA PORTILLO |
| Green Building Rough | 1/21/2025 | Approved | LILIANA PORTILLO |
| Insulation | 1/21/2025 | Approved | LILIANA PORTILLO |