1955 S BENTLEY AVE 90025

Certificate Information: 1955 S BENTLEY AVE 90025

Application / Permit
24014-10000-03947
Plan Check / Job No.
B24LA21142
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** Addition to and conversion of (e) detached garage to an ADU per LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 12/2/2024
Issuing Office
Current Status
CofO Issued on 10/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/5/2024 APPLICANT
Assigned to Plan Check Engineer 9/9/2024 EDWIN ESPIN
Corrections Issued 9/10/2024 EDWIN ESPIN
Applicant returned to address corrections 10/21/2024 EDWIN ESPIN
Plan Check Approved 10/29/2024 EDWIN ESPIN
Issued 12/2/2024 APPLICANT
CofO in Progress 10/8/2025 MICHAEL ALLEN
Permit Finaled 10/15/2025 RICHARD STEINBACH
CofO Issued 10/15/2025 RICHARD STEINBACH
Permit Finaled 10/15/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 9/16/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 9/16/2024 DARIN LAM
Sewer availability Cleared 9/16/2024 DARIN LAM
Grading Pre-Inspection Cleared 9/16/2024 VASIL MIHALEV
Roof/Waste drainage to street Cleared 9/17/2024 DARIN LAM
Specific Plan Cleared 10/9/2024 FREDDY GARCIA
GPI Written Notices Cleared 10/21/2024 EDWIN ESPIN

Contact Information

Architect Mizuki,, Steve Massanori; Lic. No.: NA22676       ,
Contractor Top Legacy Construction Inc; Lic. No.: 1043638-B       ,
Engineer Kennedy,, Nicholas; Lic. No.: S6884 3664 FENWAY STREET      FOREST GROVE, OR 97116

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/4/2024 Partial Inspection KIRK SANDERS
PLUMBING-Rough 12/27/2024 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 1/10/2025 Approved KENNETH NAGLE
METHANE-Barrier 1/10/2025 Approved KENNETH NAGLE
METHANE-Subgrade 1/10/2025 Approved KENNETH NAGLE
Footing/Foundation/Slab 2/11/2025 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 3/25/2025 Conditional Approval KIRK SANDERS
Special/Order Compliance 3/25/2025 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 4/18/2025 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 4/18/2025 Approved ARAM AVEDISIAN
PLUMBING-Rough 4/18/2025 Approved ARAM AVEDISIAN
ELECTRICAL-Final 4/23/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 4/23/2025 Conditional Approval KIRK SANDERS
Sewer 4/23/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 4/29/2025 Corrections Issued JAYLIN GRAVITTE
BUILDING-Rough-Frame 4/30/2025 Partial Approval KIRK SANDERS
Green Building Rough 4/30/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 4/30/2025 Partial Approval KIRK SANDERS
MERV13>=Rough 4/30/2025 Approved KIRK SANDERS
BUILDING-Rough-Frame 5/1/2025 Approved KIRK SANDERS
Insulation 5/1/2025 Approved KIRK SANDERS
Drywall Nailing 5/5/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 5/28/2025 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 5/30/2025 Approved KIRK SANDERS
Special/Order Compliance 6/10/2025 Corrections Issued KIRK SANDERS
Underground Mechanical 6/10/2025 Partial Approval KIRK SANDERS
Final 6/26/2025 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 6/26/2025 Approved ARAM AVEDISIAN
Gas Test 6/26/2025 Approved ARAM AVEDISIAN
Green Building Final 6/26/2025 Approved ARAM AVEDISIAN
MERV13>=Final 6/26/2025 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 6/26/2025 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 6/26/2025 Approved ARAM AVEDISIAN
ELECTRICAL-Final 10/7/2025 Approved MICHAEL ALLEN
Final 10/7/2025 OK to Issue CofO MICHAEL ALLEN
HVAC-Final 10/7/2025 Approved MICHAEL ALLEN
PLUMBING-Final 10/7/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 10/7/2025 SGSOV Approved MICHAEL ALLEN