1955 S BENTLEY AVE 90025
Certificate Information: 1955 S BENTLEY AVE 90025
- Application / Permit
- 24014-10000-03947
- Plan Check / Job No.
- B24LA21142
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** Addition to and conversion of (e) detached garage to an ADU per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 12/2/2024
- Issuing Office
- Current Status
- CofO Issued on 10/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2024 | EDWIN ESPIN |
| Corrections Issued | 9/10/2024 | EDWIN ESPIN |
| Applicant returned to address corrections | 10/21/2024 | EDWIN ESPIN |
| Plan Check Approved | 10/29/2024 | EDWIN ESPIN |
| Issued | 12/2/2024 | APPLICANT |
| CofO in Progress | 10/8/2025 | MICHAEL ALLEN |
| Permit Finaled | 10/15/2025 | RICHARD STEINBACH |
| CofO Issued | 10/15/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/15/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 9/16/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2024 | DARIN LAM |
| Sewer availability | Cleared | 9/16/2024 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 9/16/2024 | VASIL MIHALEV |
| Roof/Waste drainage to street | Cleared | 9/17/2024 | DARIN LAM |
| Specific Plan | Cleared | 10/9/2024 | FREDDY GARCIA |
| GPI Written Notices | Cleared | 10/21/2024 | EDWIN ESPIN |
Contact Information
| Architect | Mizuki,, Steve Massanori; Lic. No.: NA22676 | , |
| Contractor | Top Legacy Construction Inc; Lic. No.: 1043638-B | , |
| Engineer | Kennedy,, Nicholas; Lic. No.: S6884 | 3664 FENWAY STREET FOREST GROVE, OR 97116 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/4/2024 | Partial Inspection | KIRK SANDERS |
| PLUMBING-Rough | 12/27/2024 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 1/10/2025 | Approved | KENNETH NAGLE |
| METHANE-Barrier | 1/10/2025 | Approved | KENNETH NAGLE |
| METHANE-Subgrade | 1/10/2025 | Approved | KENNETH NAGLE |
| Footing/Foundation/Slab | 2/11/2025 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2025 | Conditional Approval | KIRK SANDERS |
| Special/Order Compliance | 3/25/2025 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 4/18/2025 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 4/18/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/18/2025 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 4/23/2025 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 4/23/2025 | Conditional Approval | KIRK SANDERS |
| Sewer | 4/23/2025 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 4/29/2025 | Corrections Issued | JAYLIN GRAVITTE |
| BUILDING-Rough-Frame | 4/30/2025 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 4/30/2025 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 4/30/2025 | Partial Approval | KIRK SANDERS |
| MERV13>=Rough | 4/30/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/1/2025 | Approved | KIRK SANDERS |
| Insulation | 5/1/2025 | Approved | KIRK SANDERS |
| Drywall Nailing | 5/5/2025 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 5/28/2025 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 5/30/2025 | Approved | KIRK SANDERS |
| Special/Order Compliance | 6/10/2025 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 6/10/2025 | Partial Approval | KIRK SANDERS |
| Final | 6/26/2025 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 6/26/2025 | Approved | ARAM AVEDISIAN |
| Gas Test | 6/26/2025 | Approved | ARAM AVEDISIAN |
| Green Building Final | 6/26/2025 | Approved | ARAM AVEDISIAN |
| MERV13>=Final | 6/26/2025 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 6/26/2025 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 6/26/2025 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 10/7/2025 | Approved | MICHAEL ALLEN |
| Final | 10/7/2025 | OK to Issue CofO | MICHAEL ALLEN |
| HVAC-Final | 10/7/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 10/7/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 10/7/2025 | SGSOV Approved | MICHAEL ALLEN |