2404 N BIRKDALE ST 90031

Certificate Information: 2404 N BIRKDALE ST 90031

Application / Permit
24014-10000-03933
Plan Check / Job No.
B24LA20978
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. SECOND STORY ADDITION AND REMODEL TO EXISTING 1 STORY SINGLE FAMILY DWELLING W/ ATTACHED GARAGE.
Permit Issued
Issued on 4/7/2025
Issuing Office
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2024 APPLICANT
Assigned to Plan Check Engineer 9/5/2024 ARSALAN SHABESTARI
Corrections Issued 9/7/2024 ARSALAN SHABESTARI
Quality Review Completed 9/16/2024 YOUNG KIM
Applicant returned to address corrections 2/10/2025 ARSALAN SHABESTARI
Plan Check Approved 3/27/2025 ARSALAN SHABESTARI
Issued 4/7/2025 APPLICANT
CofO in Progress 5/28/2026 ALIZAH MAYAGOITIA
Permit Finaled 5/28/2026 DEROLD HAUFF
CofO Issued 5/28/2026 DEROLD HAUFF
Permit Finaled 5/28/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/9/2024 JESSICA OPINION
Roof/Waste drainage to street Cleared 9/9/2024 JESSICA OPINION
Sewer availability Cleared 9/9/2024 JESSICA OPINION
ZI Cleared 12/5/2024 JASON CHAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/5/2025 Approved JEFFREY MEAD
Excavation/Setback/Form/Re-Bar 6/12/2025 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 6/12/2025 Approved HAMIK HARTOUNIAN
Sewer 6/24/2025 Approved HAMIK HARTOUNIAN
Underground Mechanical 6/24/2025 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/1/2025 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/19/2025 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 9/24/2025 Partial Inspection OSVALDO PARAMO
ELECTRICAL-Rough 9/29/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 10/2/2025 Approved HAMIK HARTOUNIAN
Underground Mechanical 10/2/2025 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 10/3/2025 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 10/15/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/7/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 11/7/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/7/2025 Partial Approval HAMIK HARTOUNIAN
MERV13>=Rough 11/7/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/13/2025 Approved HAMIK HARTOUNIAN
Insulation 11/13/2025 Approved DEVON JACKSON
Shower Pan 11/13/2025 Approved DEVON JACKSON
Interior/Exterior Lathing 11/19/2025 Approved ALEX COLIN
Drywall Nailing 11/20/2025 Not Ready for Inspection DEVON JACKSON
Drywall Nailing 11/25/2025 Approved GEM DE OCAMPO
Final 5/26/2026 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 5/26/2026 Approved HAMIK HARTOUNIAN
MERV13>=Final 5/26/2026 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 5/26/2026 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 5/26/2026 Approved HAMIK HARTOUNIAN