718 1/2 N BLADES ST 90063
Certificate Information: 718 1/2 N BLADES ST 90063
- Application / Permit
- 24014-10000-03922
- Plan Check / Job No.
- B24LA20907
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN.* Convert (E) garage to ADU w/ 2-story addition. Resulting in 2-story ADU per LAMC 12.22 A.33(c) and (d). "COMPLY WITH DEPARTMENT ORDER effective date 07/09/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS Case Number is 1008291.
- Permit Issued
- Issued on 5/15/2025
- Issuing Office
- Current Status
- Issued on 5/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/19/2024 | HUAN LE |
| Corrections Issued | 11/27/2024 | HUAN LE |
| Quality Review Completed | 12/4/2024 | JOSE RODRIGUEZ |
| Applicant returned to address corrections | 3/28/2025 | HUAN LE |
| Plan Check Approved | 4/29/2025 | HUAN LE |
| Issued | 5/15/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/31/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 12/31/2024 | WALLIE JONG |
| Clean Up Green Up | Cleared | 3/19/2025 | DANIEL CORONADO |
| Eng Process Fee Ord 176,300 | Cleared | 3/20/2025 | WALLIE JONG |
| Sewer availability | Cleared | 3/20/2025 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Segovia,, Felipe; Lic. No.: C41102 | 2622 DORSET DR TORRANCE, CA 90503 |
Inspector Information
| DANIEL DELACRUZ, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO SIERRA, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MINASSIANS, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 10/23/2025 | Not Ready for Inspection | PEDRO SIERRA |
| Gas Test | 10/23/2025 | Approved | PEDRO SIERRA |
| PLUMBING-Rough | 10/23/2025 | Partial Inspection | PEDRO SIERRA |
| Sewer | 10/23/2025 | Approved | PEDRO SIERRA |
| Footing/Foundation/Slab | 10/31/2025 | Approved | PEDRO SIERRA |
| BUILDING-Rough-Frame | 1/22/2026 | Approved | PEDRO SIERRA |
| Green Building Rough | 1/22/2026 | Approved | PEDRO SIERRA |
| Rough-Elec/Plmb/HVAC | 1/22/2026 | Approved | PEDRO SIERRA |
| Interior/Exterior Lathing | 1/29/2026 | Approved | PEDRO SIERRA |
| Drywall Nailing | 2/23/2026 | Approved | PEDRO SIERRA |
| Insulation | 2/23/2026 | Approved | PEDRO SIERRA |
| Interior/Exterior Lathing | 3/13/2026 | Approved | PEDRO SIERRA |
| Final | 5/19/2026 | Not Ready for Inspection | PEDRO SIERRA |
| Green Building Final | 5/19/2026 | Not Ready for Inspection | PEDRO SIERRA |
| SGSOV-Seismic Gas S/O Valve | 5/19/2026 | SGSOV Approved | PEDRO SIERRA |
| Service/Power Release | 5/19/2026 | Approved | PEDRO SIERRA |
| Smoke Detectors | 5/19/2026 | Approved | PEDRO SIERRA |