16000 W HORACE ST 91344

Certificate Information: 16000 W HORACE ST 91344

Application / Permit
24014-10000-03918
Plan Check / Job No.
B24LA20869
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ATTACHED COVERED PATIO AND (N) BATHROOM ADDITION TO (E) 1-STORY SFD
Permit Issued
Issued on 1/7/2025
Issuing Office
Metro
Current Status
Issued on 1/7/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/3/2024 APPLICANT
Assigned to Plan Check Engineer 9/6/2024 MINA HABILI
Corrections Issued 9/7/2024 MINA HABILI
Building Plans Picked Up 9/11/2024 APPLICANT
Applicant returned to address corrections 11/25/2024 EDWIN MARTINEZ
Plan Check Approved 12/27/2024 DANIEL SMILEY
Issued 1/7/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/24/2024 BIAINA HARITUNIAN
Sewer availability Cleared 9/24/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/27/2024 BIAINA HARITUNIAN
ZA Case Cleared 10/4/2024 DALIA MOKAYED

Contact Information

Architect Hovsepyan,, Ara; Lic. No.: C39097 611 N BRAND BLVD #1300      GLENDALE, CA 91203
Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/25/2025 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 2/25/2025 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 3/10/2025 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 3/10/2025 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 3/10/2025 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 6/27/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 6/27/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 6/27/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 6/27/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Wood Frame 6/27/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 7/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 7/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Wood Frame 7/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 7/31/2025 Partial Approval CHRISTOPHER ROJAS
Green Building Rough 7/31/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Wood Frame 7/31/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/25/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 8/25/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 8/25/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 8/25/2025 Approved CHRISTOPHER ROJAS
Wood Frame 8/25/2025 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 9/8/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 4/28/2026 Approved CHRISTOPHER ROJAS