4168 W EDENHURST AVE 90039

Certificate Information: 4168 W EDENHURST AVE 90039

Application / Permit
24014-10000-03892
Plan Check / Job No.
B24LA20692
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: NEW 12'-4" x 18'-9" IRREG.SHAPED ADDITION TO (E) SFD. ADD 3 AWNINGS. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 1/23/2025
Issuing Office
Current Status
CofO Issued on 8/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2024 APPLICANT
Assigned to Plan Check Engineer 9/6/2024 ISIS ARGUETA
Corrections Issued 9/9/2024 ISIS ARGUETA
Applicant returned to address corrections 10/16/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 11/21/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 11/22/2024 MIROOSH KHACHATOORIAN
Issued 1/23/2025 APPLICANT
CofO in Progress 8/27/2025 NICHOLAS LOPEZ
Permit Finaled 8/29/2025 DEROLD HAUFF
CofO Issued 8/29/2025 DEROLD HAUFF
Permit Finaled 8/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/26/2024 DAVID LOPEZ
Sewer availability Cleared 9/26/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 10/15/2024 DAVID LOPEZ

Contact Information

Architect Chhan,, Danny; Lic. No.: C37636 14622 CALIFORNIA AVENUE      BALDWIN PARK, CA 91706
Contractor Highground Builders; Lic. No.: 1042579-B       ,
Contractor Highground Solutions Inc.; Lic. No.: 1042579-B       ,
Engineer Schwartz,, Eric; Lic. No.: C81191 3451 GRIFFITH PARK BLVD      LOS ANGELES, CA 90027

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/30/2025 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 2/21/2025 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 3/28/2025 Approved NICHOLAS LOPEZ
PLUMBING-Rough 3/28/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Rough 4/1/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Approved NICHOLAS LOPEZ
Insulation 4/2/2025 Partial Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 4/8/2025 Not Ready for Inspection NICHOLAS LOPEZ
Drywall Nailing 4/8/2025 Partial Approval NICHOLAS LOPEZ
HVAC-Rough 4/8/2025 Not Ready for Inspection NICHOLAS LOPEZ
Insulation 4/8/2025 Not Ready for Inspection NICHOLAS LOPEZ
Interior/Exterior Lathing 4/8/2025 Partial Approval NICHOLAS LOPEZ
Shower Pan 4/8/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 4/10/2025 Approved NICHOLAS LOPEZ
Green Building Rough 4/10/2025 Conditional Approval NICHOLAS LOPEZ
Insulation 4/10/2025 Partial Approval NICHOLAS LOPEZ
Interior/Exterior Lathing 4/10/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 4/16/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/16/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 5/5/2025 Partial Approval REGINA MENDEZ
BUILDING-Rough-Frame 8/11/2025 Approved BRENDAN MORELLI
Final 8/11/2025 Corrections Issued BRENDAN MORELLI
Green Building Final 8/11/2025 Not Ready for Inspection BRENDAN MORELLI
Green Building Rough 8/11/2025 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 8/11/2025 SGSOV Approved BRENDAN MORELLI
Smoke Detectors 8/11/2025 Approved BRENDAN MORELLI
Final 8/15/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 8/15/2025 Approved NICHOLAS LOPEZ
Final 8/26/2025 OK to Issue CofO NICHOLAS LOPEZ