5108 3/4 E YORK BLVD 90042
Certificate Information: 5108 3/4 E YORK BLVD 90042
- Application / Permit
- 24014-10000-03873
- Plan Check / Job No.
- B24LA20466
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN Proposed addition to existing garage to be converted into ADU per LAMC 12.22A.33(c) and (d)
- Permit Issued
- Issued on 4/2/2025
- Issuing Office
- Current Status
- CofO Issued on 9/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2024 | NGHI SU |
| Corrections Issued | 9/10/2024 | NGHI SU |
| Plan Check Approved | 12/23/2024 | NGHI SU |
| Issued | 4/2/2025 | APPLICANT |
| CofO in Progress | 9/19/2025 | DAVID WILLIAMS |
| Permit Finaled | 9/20/2025 | DEROLD HAUFF |
| CofO Issued | 9/20/2025 | DEROLD HAUFF |
| Permit Finaled | 9/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/16/2024 | DAVID LOPEZ |
| Address approval | Cleared | 9/18/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 10/1/2024 | DAVID LOPEZ |
| Construction near power lines | Cleared | 12/10/2024 | RIDWAN HARDY |
| Zoning Information File | Cleared | 12/12/2024 | CASEY JENSEN |
| Grading Pre-Inspection | Cleared | 12/23/2024 | NGHI SU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: NA64529 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/5/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Rough | 7/1/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 7/1/2025 | Approved | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 7/14/2025 | Approved | DAVID WILLIAMS |
| Green Building Rough | 7/14/2025 | Approved | DAVID WILLIAMS |
| HVAC-Rough | 7/14/2025 | Approved | DAVID WILLIAMS |
| Insulation | 7/14/2025 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 7/14/2025 | Approved | DAVID WILLIAMS |
| Wood Frame | 7/14/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 7/21/2025 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 9/15/2025 | Approved | DAVID WILLIAMS |
| Final | 9/15/2025 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 9/15/2025 | Corrections Issued | DAVID WILLIAMS |
| HVAC-Final | 9/15/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| PLUMBING-Final | 9/15/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 9/15/2025 | SGSOV Approved | DAVID WILLIAMS |
| Service/Power Release | 9/15/2025 | Approved | DAVID WILLIAMS |
| Smoke Detectors | 9/15/2025 | Approved | DAVID WILLIAMS |
| Final | 9/18/2025 | OK to Issue CofO | DAVID WILLIAMS |
| Green Building Final | 9/18/2025 | Approved | DAVID WILLIAMS |
| HVAC-Final | 9/18/2025 | Approved | DAVID WILLIAMS |